star-fst-l AT lists.bnl.gov
Subject: Star-fst-l mailing list
List archive
- From: "Ye, Zhenyu" <yezhenyu AT uic.edu>
- To: Maowu Nie <maowu.nie AT email.sdu.edu.cn>
- Cc: Star-fst L <star-fst-l AT lists.bnl.gov>
- Subject: [Star-fst-l] T-Board Assembly
- Date: Mon, 22 Feb 2021 22:04:12 +0000
Maowu, thanks for confirmation.
There might be one small issue. The screws of the connectors on the T-board
seem to be a little bit too long, so that it creates a small conflict with
the module peek mechanical structure (MS). See page 3 in Xu’s presentation
from last week’s FST meeting [1]. It seems to me that one can still press the
T-board to fasten with the MS through the four corner holes. But the T-board
and/or the MS has a tiny bend. As this observation is not fully consistent
with what Yi reported in [2], I have asked Yi to check again.
If the answer is yes, I see 3 options
1. Shorten the screws (I don’t think it is possible but Maowu please confirm)
2. Leave as is
3. Add a washer between T-board and MS
A related question for the group is whether we should use PEEK screws/nuts to
use to fasten T-board onto MS, as pointed out in Yi’s slides. I don’t recall
we have come to a conclusion at the meeting (?) but we should decide soon.
Please comment.
Thanks,
Zhenyu
[1]
https://drupal.star.bnl.gov/STAR/system/files/FstModuleAssemblyFeb08Feb142021.pdf
[2] https://drupal.star.bnl.gov/STAR/system/files/20201123_FST_MS_YiYang.pdf
> On Feb 22, 2021, at 3:21 PM, Maowu Nie <maowu.nie AT email.sdu.edu.cn> wrote:
>
> Hi Zhenyu,
>
> Thanks for the reminder, we will work on it.
>
> Regards,
> Maowu
>
>
>> On Feb 22, 2021, at 11:07 PM, Ye, Zhenyu <yezhenyu AT uic.edu> wrote:
>>
>> Hi Maowu, Jianing,
>>
>> We have tested the new T-boards/purple cables in the readout and found no
>> problem.
>> Please go ahead with the T-board assembly and testing.
>>
>> Best,
>> Zhenyu
>>
>>> On Nov 11, 2020, at 4:12 AM, Maowu Nie <maowu.nie AT email.sdu.edu.cn> wrote:
>>>
>>> Hi Mike and Yi,
>>>
>>> We just finished the QC test of the first 10 sets of T-board , and will
>>> send them to you soon.
>>>
>>> Please confirm the following address for you is correct or not:
>>>
>>> 8 sets to Mike:
>>> Brookhaven National Laboratory, Shipping Department- Building 98 Upton,
>>> NY 11973,
>>> Michael Capotosto, capotosto AT bnl.gov.
>>>
>>> 2 sets to Yi:
>>> No.1 University Rd., East District, Tainan City, 70101
>>> National Cheng Kung University, Department of Physics,
>>> Yi Yang
>>>
>>> One thing I need to mention to you, the nuts in the connector have the
>>> shedding risk.
>>> So when you do installation, please make sure the screw is well tightened.
>>>
>>> Regards,
>>> Maowu
>>>
>>>
>>>
>>>
>>>
>>
>>
>
-
[Star-fst-l] T-Board Assembly,
Ye, Zhenyu, 02/22/2021
-
Re: [Star-fst-l] T-Board Assembly,
Visser, Gerard, 02/22/2021
-
Re: [Star-fst-l] T-Board Assembly,
Yi Yang, 02/23/2021
-
Re: [Star-fst-l] T-Board Assembly,
Visser, Gerard, 02/23/2021
-
Re: [Star-fst-l] T-Board Assembly,
Yi Yang, 02/23/2021
-
Re: [Star-fst-l] T-Board Assembly,
Capotosto, Michael, 02/23/2021
- Re: [Star-fst-l] T-Board Assembly, Visser, Gerard, 02/23/2021
-
Re: [Star-fst-l] T-Board Assembly,
Capotosto, Michael, 02/23/2021
-
Re: [Star-fst-l] T-Board Assembly,
Yi Yang, 02/23/2021
-
Re: [Star-fst-l] T-Board Assembly,
Visser, Gerard, 02/23/2021
-
Re: [Star-fst-l] T-Board Assembly,
Yi Yang, 02/23/2021
-
Re: [Star-fst-l] T-Board Assembly,
Maowu Nie, 02/23/2021
- Re: [Star-fst-l] T-Board Assembly, Ye, Zhenyu, 02/23/2021
-
Re: [Star-fst-l] T-Board Assembly,
Visser, Gerard, 02/22/2021
Archive powered by MHonArc 2.6.24.