Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - Re: [Usatlas-hllhc-lartl2l3-l] LAr HL-LHC weekly mtg

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>, John Hobbs <John.Hobbs AT stonybrook.edu>, kj <johns AT physics.arizona.edu>
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] LAr HL-LHC weekly mtg
  • Date: Wed, 27 Mar 2019 22:56:53 -0400


Hi all,

I uploaded the latest draft of my
L2 overview talk (and also L3 FEB2 talk) to
the indico page of tomorrow's Scrubbing mtg
(https://indico.bnl.gov/event/5934/). If you
spot any major errors or omissions, let me
know and I can see if I still have a chance
to iterate the slides (or can at least mention
any changes in my talks).
Regards,
John

On 3/27/19 10:27 PM, John Parsons wrote:

I just got to the hotel near BNL.  I am finalizing my
sets of slides for tomorrow, and then will look
at Tim's update.  I will get to yours and Hong's
next, but maybe only tomorrow since your talks
are Friday.

    Thanks,
        John

On 3/27/19 10:11 PM, Xu, Hao wrote:
Hi John,

I updated the slides and spreadsheet on the indico.

Regards,

Hao

*From:* Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> *On Behalf Of *Ma, Hong
*Sent:* Wednesday, March 27, 2019 6:23 PM
*To:* Parsons, John <parsons AT nevis.columbia.edu>; usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
*Subject:* Re: [Usatlas-hllhc-lartl2l3-l] LAr HL-LHC weekly mtg

                 I updated my slides on the indico.

https://indico.bnl.gov/event/5917/

                 Hong.

*From: *Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov <mailto:usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov>> on behalf of John Parsons <parsons AT nevis.columbia.edu <mailto:parsons AT nevis.columbia.edu>>
*Date: *Wednesday, March 27, 2019 at 1:43 PM
*To: *"usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <mailto:usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <mailto:usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>>
*Subject: *Re: [Usatlas-hllhc-lartl2l3-l] LAr HL-LHC weekly mtg

Hi all,

I uploaded a draft of the slides for my

L3 talk; comments are welcome.  I now have to work

on preparing the agenda page.  I will look later at

Hao's draft slides, and everyone else let me know

if you upload an updated version.

Regards,

John

On 3/26/19 9:45 PM, John Parsons wrote:

    Hi all,

           I give below a few quick comments on the draft slides

    posted so far.  I have also posted a preliminary version

    of my draft L2 overview slides; please take a look and

    send me comments.  (the parts about BE firmware are still

    subject to change, as we work with Kj to understand what

    is going on there, but the rest should be stable.)

               John

    Tim

    p. 15 - what does "Boundary conditions" mean in this context?

    pp. 1 - 18 - good for external review, but perhaps too long

    and detailed for internal scrubbing?  Consider shortening

    p. 24 - your signs are reversed.  Calculate new-old

           - VL+ has increased by almost $0.5M ??!!

           - I sent you costs for COLUTAv2 testboard

    and radiation testboard. Can't you use those to

    update the test jig costs?

    pp. 25-28 - include on slides previous costs, so

    direct comparison can be made

    p. 32 - "SMY"

    Andy

    p. 2 - edit to remove my email comments

    p. 5 - "US previously responsible for Carrier board...

    as well as passive RTM (similar to Phase 1)"

    p. 10 - stress that new h/w cost estimate and new

    quotes included in current Scrubbing Report

    p. 11 "better naming conventions" change to

    "adapt to ATLAS LAr naming conventions"

    - will need to add slides on solution to

    f/w cost issue, once resolved with Kj

    Hong

    p. 12 - LAUROC1 includes shaper from BNL, so stress

    a bit more the collab. and don't imply ALFE vs

    LAUROC is a "competition"

    p. 15 - "removing the future effort at U Penn"

    p. 17 - say current M&S comes from ATLAS BOE, and now

    you are ready to update with a new quote; also quantify

    difference in cost with new quote

    p. 19 - what about new quotes for test jigs, packaging?

           - "removing risks" means "retiring" or

    "implementing", or ...?

    On 3/25/19 6:59 AM, John Parsons wrote:

        Hello all,

              We will meet this week in our usual

        timeslot of Tuesday at 1 pm NY time.

        I have created an agenda page at

        https://indico.bnl.gov/event/5917/.

              The man topic will be the status

        of preparations for the Scrubbing at

        BNL on Thurs.+Fri. this week.

              In addition to the usual materials

        (RLS, BOE, ...) needed for each review,

        each L3 should prepare some introductory

        slides for the Scrubbing that cover

        the following topics:

        - very brief overview of deliverables

        and institutions involved (just to remind

        people what the L3 is about)

        - brief technical status, emphasizing

        progress since last review and upcoming

        major steps (eg. milestones) over next

        ~ 9 - 12 months

        - for NSF, description of boundary

        between preMREFC and MFREC

        - summary of changes implemented to RLS

        since previous review (discuss separately

        those covered by an approved BCP and those

        implemented in the current RLS but not

        yet approved)

        - summary of changes still needed to

        be implemented in RLS, if any.  (particularly

        relevent for BE and Syst. Integ., but others

        can point out here if they have realized

        any changes still needed)

        - updates M&S costs, due to updating quotes

        - status of Risk register, and any changes

        since last review either implemented or

        needed

              Start working right away on these

        slides, which will be important to organize and

        steer the discussion at the Scrubbing.  It is

        particularly important to present coherently

        the changes that still need to be made.  As

        soon as you have even a partial draft of the

        slides, post them to the indico page above,

        so that we can iterate together and try achieve

        some consistency across L3s.

              Talk to you tomorrow.`

              Regards,

                      John

--

______________________________________________________________________

John Parsons

Nevis Labs, Email: parsons AT nevis.columbia.edu <mailto:parsons AT nevis.columbia.edu>

   Columbia UniversityPhone: (914) 591-2820

P.O. Box 137Fax: (914) 591-8120

Irvington, NY 10533WWW: https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=vNBAsz3HyoZeuDJ-7Uf8EDevNJ8zgcEQBcVxrFCnL90&s=39b8yIXWx83txwnZykAKzyBnHOA4ot3y_v8beqO4w_k&e=

______________________________________________________________________

_______________________________________________

Usatlas-hllhc-lartl2l3-l mailing list

Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <mailto:Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>

https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l



--
______________________________________________________________________

John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW: http://www.nevis.columbia.edu/~parsons/

______________________________________________________________________




Archive powered by MHonArc 2.6.24.

Top of Page