usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets
- From: "Ma, Hong" <hma AT bnl.gov>
- To: "Parsons, John" <parsons AT nevis.columbia.edu>, "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets
- Date: Sun, 31 Mar 2019 15:24:37 +0000
I enter the following to the spreadsheet. I note the previous status as of Nov, and the current status of March.
ASIC460130: preprototype2 Final design Nov report: 90%, expected completion 12/4/2018 March report: 100%, actual completion, 12/4/2018
ASIC460140: Submission Nov Report: 50% expected completion: 12/5/2018 March report: 100%, actual completion 12/6/2018
ASIC460150: Pre-Prototype2 ASIC Fabrication and Preparation for Testing and Preparation for Testing Nov report: 0% March Report: 100%. 12/7/2018 to 2/28/2019
ASIC460160: Pre-Prototype2 ASIC Packaging and Preparation for Testing and Preparation for Testing Nov report: 0% March report 100%, 3/1/2019 to 3/25/2019
ASIC460160M: Material for preprototype2 Nov report: 100% completed.
ASIC460180: Pre-Prototype2 Main Board Schematics Design and Preparation for Testing Nov report: 90%, expected completion 12/15/2018 March Report: 100%, actual: 1/15/2019
ASIC460190: Pre-prototype2 Main Board Layout Design Nov report: 0% March report: 100%, actual: 1/15/2019 to 2/28/2019
ASIC460200: Pre-Prototype2 Main Board Fabrication ASIC460200M: Material for Pre-Prototype2 Main Board Fabrication Nov report 0% March report: 95% complete. Actual start: 3/1/2019, expected 4/5/2019
ASIC460200T: 0%
ASIC460210: Pre-Prototype2 ASIC Evaluation Test Nov report: 0% March report:: 5% complete, actual start 3/29/2019, expected completion 4/30/2019
Hong.
From:
Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
FYI, we need to fill out a new statusing. Instructions are given below. Please take care of this asap.
John
-------- Forwarded Message -------- Subject: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets Date: Tue, 26 Mar 2019 20:14:28 +0000 From: Freedman, Rhoumela <rfreedman AT bnl.gov> To: Novakova, Penka N <penka AT bnl.gov>,
Hi everyone,
I created Filter views under people’s last names. Let me know if you have any questions.
Thank you,
Rhoumela
*From:* Novakova, Penka N *Sent:* Tuesday, March 26, 2019 11:13 AM *Cc:* Freedman, Rhoumela <rfreedman AT bnl.gov>; Kotcher, Jonathan <kotcher AT bnl.gov>; Gustaaf Brooijmans (gusbroo AT nevis.columbia.edu) <gusbroo AT nevis.columbia.edu>; Hal Evans (hgevans AT indiana.edu) <hgevans AT indiana.edu>; Michael Tuts (tuts AT pmtuts.net) <tuts AT pmtuts.net>; Heidi Crookston <heidi.crookston AT mrcpmcs.com> *Subject:* Schedule status sheets
Dear All,
Following the major schedule updates, we are starting monthly status reporting. At this time we ask you to report on the status of work done *through March 31, 2019*.
The files are in google docs and need to be updated online – DO NOT download the files.
* 6.01 – Pixels - * 6.02 – Strips - * 6.03 – Global Mechanics - * 6.04 – LAr - * 6.05 – Tile - * 6.06 – Muon - * 6.07 – DAQ - * 6.08 Trigger -
The reports are at L2. The CAMs can filter for their name in column C and the ICs can filter for their institute in column D. The previous status is available in column J - “Prior % complete”. In some cases activity IDs have been changed so we had to map the "Prior % complete” to the activities. Please excuse us if there are some inconsistencies. We hope to resolved this next month and the following months when P6 is updated with latest status. The report contain activities for many months and therefore they are fairly large. We kept the 100% completed activities for you to review.
Please provide status in columns K, L, M and N. Make sure that you enter the actual start date for all started activities and finish date for all activities that are 100% completed, this information is crucial when we update the schedule in P6. If the activity is completed but you do not remember the exact start and finish dates you can enter your best estimate or copy the dates from columns H and I. All activities that have been completed/started between December 1, 2018 and March 31, 2019 need to be statussed. In actual start/finish dates do NOT enter dates after March 31, 2019, this confuses the system.
Please complete the status reports by Tuesday, April 2.
We expect that the L2 managers and deputies will notify us (Penka, Heidi, Carrie) as soon as the status for their system is complete.
Let us know if you have any questions, and also any comments to make the process smoother and more user-friendly.
Thank you for your cooperation.
Penka, Heidi, Carrie
Penka Novakova
U.S. ATLAS HL-LHC Project Office
Bldg. 510
Brookhaven National Lab
Upton, NY 11973
Tel. 631-344-2502
|
-
[Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
John Parsons, 03/29/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Ma, Hong, 03/31/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
John Parsons, 03/31/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Ma, Hong, 03/31/2019
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets, John Parsons, 03/31/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Ma, Hong, 03/31/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
John Parsons, 03/31/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: Re: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Ma, Hong, 03/31/2019