I completed most of the rest of the new Cost&Schedule slides for the FEB2, leaving just the "guided drilldown" to do still. I updated my slides at https://indico.bnl.gov/event/18946/.
John
On 4/1/23 3:10 PM, John Parsons wrote:
Hi all,
As we discussed, I have gone through the various BCPs and produced a table summarizing the delays for each L3. I have put this new table in the draft of my FEB2 "Cost&Schedule" slides, and uploaded them to yesterday's Indico (https://indico.bnl.gov/event/18946/). The table is all I have done so far on those new slides so far, and it is on p. 7 of those slides; Tim and Andy should put a similar slide with a copy of the same table in their L3 Cost&Schedule slides.
As additional info, here are the milestones I used to quantify the delays at L3, and their respective dates currently and at the start of the MREFC:
6.4.1
FEE20940 (Milestone: ADC Production Complete)
Current date: 24-Jun-25
MREFC start date: 9-Jan-24
6.4.3
BEE11060 (Milestone: BE Acceptance Test Complete)
Current date: 30-Sep-26
MREFC start date: 3-Jan-25
Regards,
John
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!H1bdSGEZw4cnp8h6bBjryBovLY9BdrusbICvb1q1J0X8AVD2IXCFzEzCxAobj4-egtVqUOah1SjQdw2LgICC5yVEnwJUJXzAx-OiRMWW5wCb0w$
______________________________________________________________________
-
[Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
John Parsons, 04/01/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
John Parsons, 04/01/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
Ma, Hong, 04/01/2023
- Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks, John Parsons, 04/02/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
John Parsons, 04/03/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
Andy Haas, 04/03/2023
- Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks, Tim Andeen, 04/03/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
John Parsons, 04/04/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
Tim Andeen, 04/04/2023
- Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks, Ma, Hong, 04/04/2023
- Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks, John Parsons, 04/05/2023
- Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks, Ma, Hong, 04/05/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
Tim Andeen, 04/04/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
Andy Haas, 04/03/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
Ma, Hong, 04/01/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks,
John Parsons, 04/01/2023
Archive powered by MHonArc 2.6.24.