Hello colleagues,
Not unexpectedly, as part of the ePIC e-endcap tracker optimization, the space allocated for the pfRICH was reduced by 5cm along the beam line.
Alex, please we need realistic estimates of the overall envelope for the pfRICH vessel, especially at Rmax, Zmin and Zmax. Remember, the v03 pfRICH GDML geometry was still in a "few mm overlap" conflict with the neighboring subdetectors, meaning the clearances
may have not been observed strictly, even before this 5cm reduction.
Then we check with Chandra what the implications on the pfRICH performance are.
All in all, it sounds like we should discuss the incorporation of other possible pfRICH extensions (either pyramid funneling mirrors or a second aerogel layer a la Belle II or both) in the baseline configuration at our Thursday meeting, before the transition
from mRICH to pfRICH is concluded in P6.
Regards,
Alexander.
-
[Eic-projdet-pfrich-l] pfRICH space reduced by 5cm,
Kiselev, Alexander, 06/12/2023
-
Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm,
Nikolai Smirnov, 06/13/2023
- Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm, Aschenauer, Elke, 06/13/2023
- <Possible follow-up(s)>
-
Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm,
Kiselev, Alexander, 06/13/2023
- Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm, Aschenauer, Elke, 06/13/2023
-
Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm,
Nikolai Smirnov, 06/13/2023
-
Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm,
Kiselev, Alexander, 06/16/2023
-
Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm,
Nikolai Smirnov, 06/19/2023
- Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm, Aschenauer, Elke, 06/19/2023
-
Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm,
Nikolai Smirnov, 06/19/2023
-
Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm,
Kiselev, Alexander, 06/16/2023
-
Re: [Eic-projdet-pfrich-l] pfRICH space reduced by 5cm,
Nikolai Smirnov, 06/13/2023
Archive powered by MHonArc 2.6.24.