Hi Flemming,

Sorry for the late reply. Please find my updated slides in the following link:

Comments and suggestions are welcome.

Best,

Xu

On Tue, Jul 28, 2020 at 1:55 PM videbaek <videbaek AT bnl.gov> wrote:



Hi

Here are some comments to what should be in the talk: Rahul, Sun, Maowu
the comments are also in word document

best
Flemming


Assembly UIC/FNAL


There has to be a slide on the Q&A done during production as we talk
about on Monday
// slide 11
Test to be performed –
Amount on time –
Tracking of outcome (how recorded)

Check of temperature of APV chips with infrared sensor/camera. With
cooled water
Maybe done at UIC or at BNL -TDB

Mentioned that this will be repeated when they arrive/assembled in at
BNL

Need a slide that details just in words the step for assembly

You can keep the summary,
But on slide before take the assembly tasks – put into a 3 column table
with col 2 == time
(days () , -- also is there no steps for curing time and column 3 with
institution/man power

Repeat the number of assemblies to make; what can be done in parallel
This is important information to evaluate the 3 months

--
Add an ESH slide describing the additional materials used in assembly
(like glue, epoxy for encapsulation)
Add statement that you follow UIC guidelines for working safely in the
lab.



Hybrid & T-boards

Slide 5 ; reformulate the waiting for .. as we discussed.
I assume we agreed we would not change mechanics for the T-board, but
move the capacitor on the board. Add a week for that task, (design +
signoff by group)

You got my estimate for connectors-
I suggest the make production slide into two
One for hybrid and one for T-board – you might indicator vendor –
Based on experience with prototype.
Give the quantities being made

One slide with ES&H
Materials proper (is there a standard that is being followed
--- non flammable PCB ?
Work at lab at SDU minimal. Follows University work rules.


Integration

Rahul

Please add a slide on ES&H

That we follow BNL rules
There will be safety review (before actual production?)
Certainly, one before installation
Any specific concern that you pay attention to on this

Also if you can add a slide where you discuss your response to Charge
questions?
(Those relevant  like installation schedule)





--
Flemming Videbaek
senior scientist
videbaek @ bnl.gov
Brookhaven National Lab
Physics Department
Bldg 510D
Upton, NY 11973

phone: 631-344-4106
cell     :  631-681-1596_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l



Archive powered by MHonArc 2.6.24.

Top of Page