usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1
- From: Michael Tuts <tuts AT pmtuts.net>
- To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>, "Fisher, Wade" <fisherw AT msu.edu>, Tim Andeen <timothy.robert.andeen AT cern.ch>, "Schwienhorst, Reinhard" <schwier AT msu.edu>, "Novakova, Penka N" <penka AT bnl.gov>, "Michael Tuts" <tuts AT nevis.columbia.edu>
- Cc: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1
- Date: Tue, 17 Aug 2021 22:58:57 +0000
Hi All,
I made a backup slide for my talk tomorrow regarding scientific (uncosted)
labor (based on the July IPD file for time phased NSF FTE but filtering on
"...U_COST_..." resources. The first tab shows it for L2 with a plot, and the
second tab shows the detail for each WBS L3 with a list of the specific
uncosted resources. Maybe this is helpful should the issue come up tomorrow -
not that I expect it to, but you never know.
Cheers, Mike
-----Original Message-----
From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
Sent: Tuesday, August 17, 2021 2:51 PM
To: Fisher, Wade <fisherw AT msu.edu>; Tim Andeen
<timothy.robert.andeen AT cern.ch>; Schwienhorst, Reinhard <schwier AT msu.edu>;
Novakova, Penka N <penka AT bnl.gov>; Michael Tuts <tuts AT nevis.columbia.edu>
Subject: Re: Some notes from CAM interviews - day 1
Hi,
So where this is particularly relevant from an EVMS perspective is that since
we don't pay for scientific labor, it doesn't enter any of the standard EVMS
metrics (it has $0 BCWS, BCWP and ACWP). The usual follow-up question is
"how do you measure progress then"? And our answer is that almost every task
with uncosted labor has at least as much costed labor.
Best,
Gustaaf
On 8/17/21 2:23 PM, Fisher, Wade wrote:
> Hi Gustaaf,
>
> Yes, Carrie also sent a correction on the uncosted labor. Somehow I
> had gotten it into my mind that the question was about costed
> scientific labor and couldn't turn my brain around after that. Thanks
> for trying to get me on the right path, though!
>
> Best regards,
> Wade
>
> --
> Wade Fisher -*- Professor of Physics Department of Physics and
> Astronomy Michigan State University Biomedical and Physical Sciences
> Building
> 567 Wilson Road, Rm 3233
> East Lansing, MI 48824
>
> MSU Office: 517-884-5556
> CERN Office: 32 2-B03 * 76-71756
> Fax MSU: 517-355-6661
> https://urldefense.com/v3/__http://www.pa.msu.edu/*fisherw/__;fg!!P4SdNyxKAPE!Xx7TqEOPoPQBDTMlZbKcNSJGWC_xTaX8KY-BidHNDQDTz-wlP9wWvXcA2lf4taHYl8viNNy3INo0TKXKIoKYP5flBAeb$
>
> <https://urldefense.com/v3/__http://www.pa.msu.edu/*fisherw/__;fg!!P4SdNyxKAPE!Xx7TqEOPoPQBDTMlZbKcNSJGWC_xTaX8KY-BidHNDQDTz-wlP9wWvXcA2lf4taHYl8viNNy3INo0TKXKIoKYP5flBAeb$
> >
> ----------------------------------------------------------------------
> --
> *From:* Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
> *Sent:* Tuesday, August 17, 2021 2:14 PM
> *To:* Fisher, Wade <fisherw AT msu.edu>; Tim Andeen
> <timothy.robert.andeen AT cern.ch>; Schwienhorst, Reinhard
> <schwier AT msu.edu>; Novakova, Penka N <penka AT bnl.gov>; Michael Tuts
> <tuts AT nevis.columbia.edu>
> *Subject:* Some notes from CAM interviews - day 1
>
> Hello Wade,
>
> Well done. A few small mistakes listed below. Two are also relevant
> for Tim and Reinhard, so cc'd.
>
> -Yes, there is uncosted labor in the 6.8.3 RLS. Quite a bit.
>
> -Schedule variance and cost variance are independent! A schedule
> variance does not create a cost variance and vice-versa: a schedule
> variance refers to work not done (or done ahead of time), whereas a
> cost variance measures the difference in planned vs actual cost for
> *work done only*.
>
> -The one year delay in the schedule that was already implemented in
> the need-by dates is not COVID-related. It's due to the "original LS2"
> delay. There is likely to be another delay, that one due to covid.
>
> Best,
>
> Gustaaf
>
--
Gustaaf Brooijmans - Columbia University
@Columbia: (212) 854 4527; Nevis virtual phone: (914) 591 2804
Als sie mich holten,
gab es keinen mehr, der protestieren konnte.
Attachment:
202107TimePhaseFTENSF-Uncosted.xlsx
Description: 202107TimePhaseFTENSF-Uncosted.xlsx
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/17/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
John Parsons, 08/17/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Gustaaf Brooijmans, 08/18/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1, John Parsons, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
John Parsons, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1, John Parsons, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Gustaaf Brooijmans, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
John Parsons, 08/17/2021
Archive powered by MHonArc 2.6.24.