usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade Level 2 and Deputies-NSF only Management Mailing List
List archive
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>, Michael Tuts <tuts AT pmtuts.net>, "Fisher, Wade" <fisherw AT msu.edu>, Tim Andeen <timothy.robert.andeen AT cern.ch>, "Schwienhorst, Reinhard" <schwier AT msu.edu>, "Novakova, Penka N" <penka AT bnl.gov>, Michael Tuts <tuts AT nevis.columbia.edu>
- Cc: "Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1
- Date: Wed, 18 Aug 2021 09:54:03 -0400
I am not suggesting they should expect it to be similar across L3s, just pointing out the inconsistent definitions used. Mike's table has some L3s that are essentially dominated by L3 mgmt labor, whereas other L3s have those left out and are really about postdocs+grad students.
John
On 8/18/21 9:40 AM, Gustaaf Brooijmans wrote:
I'm not sure why you'd expect the numbers to be similar across L2s. Eg HTT has always relied (excessively) on uncosted labor. It's been a problem since day 1. And there are other cases where there is none.
On 8/18/21 9:35 AM, Michael Tuts wrote:
Unless I missed a "...U_COST..." then that is what is in the RLS though
-----Original Message-----
From: John Parsons <parsons AT nevis.columbia.edu>
Sent: Tuesday, August 17, 2021 9:06 PM
To: Michael Tuts <tuts AT pmtuts.net>; Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>; Fisher, Wade <fisherw AT msu.edu>; Tim Andeen <timothy.robert.andeen AT cern.ch>; Schwienhorst, Reinhard <schwier AT msu.edu>; Novakova, Penka N <penka AT bnl.gov>; Michael Tuts <tuts AT nevis.columbia.edu>
Cc: Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1
You should be aware that these numbers seem quite inconsistent across L2s, in particular since some show L2 and L3 management FTEs while others do not.
John
On 8/17/21 6:58 PM, Michael Tuts wrote:
Hi All,
I made a backup slide for my talk tomorrow regarding scientific (uncosted) labor (based on the July IPD file for time phased NSF FTE but filtering on "...U_COST_..." resources. The first tab shows it for L2 with a plot, and the second tab shows the detail for each WBS L3 with a list of the specific uncosted resources. Maybe this is helpful should the issue come up tomorrow - not that I expect it to, but you never know.
Cheers, Mike
-----Original Message-----
From: Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
Sent: Tuesday, August 17, 2021 2:51 PM
To: Fisher, Wade <fisherw AT msu.edu>; Tim Andeen
<timothy.robert.andeen AT cern.ch>; Schwienhorst, Reinhard
<schwier AT msu.edu>; Novakova, Penka N <penka AT bnl.gov>; Michael Tuts
<tuts AT nevis.columbia.edu>
Subject: Re: Some notes from CAM interviews - day 1
Hi,
So where this is particularly relevant from an EVMS perspective is that since we don't pay for scientific labor, it doesn't enter any of the standard EVMS metrics (it has $0 BCWS, BCWP and ACWP). The usual follow-up question is "how do you measure progress then"? And our answer is that almost every task with uncosted labor has at least as much costed labor.
Best,
Gustaaf
On 8/17/21 2:23 PM, Fisher, Wade wrote:
Hi Gustaaf,
Yes, Carrie also sent a correction on the uncosted labor. Somehow I
had gotten it into my mind that the question was about costed
scientific labor and couldn't turn my brain around after that.
Thanks for trying to get me on the right path, though!
Best regards,
Wade
--
Wade Fisher -*- Professor of Physics Department of Physics and
Astronomy Michigan State University Biomedical and Physical Sciences
Building
567 Wilson Road, Rm 3233
East Lansing, MI 48824
MSU Office: 517-884-5556
CERN Office: 32 2-B03 * 76-71756
Fax MSU: 517-355-6661
https://urldefense.com/v3/__http://www.pa.msu.edu/*fisherw/__;fg!!P4S
dNyxKAPE!Xx7TqEOPoPQBDTMlZbKcNSJGWC_xTaX8KY-BidHNDQDTz-wlP9wWvXcA2lf4
taHYl8viNNy3INo0TKXKIoKYP5flBAeb$
<https://urldefense.com/v3/__http://www.pa.msu.edu/*fisherw/__;fg!!P4
SdNyxKAPE!Xx7TqEOPoPQBDTMlZbKcNSJGWC_xTaX8KY-BidHNDQDTz-wlP9wWvXcA2lf
4taHYl8viNNy3INo0TKXKIoKYP5flBAeb$ >
---------------------------------------------------------------------
-
--
*From:* Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
*Sent:* Tuesday, August 17, 2021 2:14 PM
*To:* Fisher, Wade <fisherw AT msu.edu>; Tim Andeen
<timothy.robert.andeen AT cern.ch>; Schwienhorst, Reinhard
<schwier AT msu.edu>; Novakova, Penka N <penka AT bnl.gov>; Michael Tuts
<tuts AT nevis.columbia.edu>
*Subject:* Some notes from CAM interviews - day 1
Hello Wade,
Well done. A few small mistakes listed below. Two are also relevant
for Tim and Reinhard, so cc'd.
-Yes, there is uncosted labor in the 6.8.3 RLS. Quite a bit.
-Schedule variance and cost variance are independent! A schedule
variance does not create a cost variance and vice-versa: a schedule
variance refers to work not done (or done ahead of time), whereas a
cost variance measures the difference in planned vs actual cost for
*work done only*.
-The one year delay in the schedule that was already implemented in
the need-by dates is not COVID-related. It's due to the "original LS2"
delay. There is likely to be another delay, that one due to covid.
Best,
Gustaaf
--
Gustaaf Brooijmans - Columbia University
@Columbia: (212) 854 4527; Nevis virtual phone: (914) 591 2804
Als sie mich holten,
gab es keinen mehr, der protestieren konnte.
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-
l
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW: https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!RMCHNiN2WR7GJMOGQylJUzmYbhnJSCTlCMBXVj0JW2F2-xUbxhnRSOuveexKeMnAJlpbOz_pjVAfnd0XzHaDeRmVxfRd$
______________________________________________________________________
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!RMCHNiN2WR7GJMOGQylJUzmYbhnJSCTlCMBXVj0JW2F2-xUbxhnRSOuveexKeMnAJlpbOz_pjVAfnd0XzHaDeRmVxfRd$
______________________________________________________________________
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/17/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
John Parsons, 08/17/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Gustaaf Brooijmans, 08/18/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1, John Parsons, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
John Parsons, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1, John Parsons, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Gustaaf Brooijmans, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
Michael Tuts, 08/18/2021
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] Some notes from CAM interviews - day 1,
John Parsons, 08/17/2021
Archive powered by MHonArc 2.6.24.