Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: John Parsons <parsons AT nevis.columbia.edu>
  • To: "Ma, Hong" <hma AT bnl.gov>
  • Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
  • Date: Fri, 10 Mar 2023 13:54:12 -0500


Hi all,

Just got back to NYC from a productive LAr week!
As Hong explained, we need to finalize SOON the two RRs (ie. the "regular" one and the "supply chain" one), so that the MC can be run in advance of freezing everything for the NSF rebaseline review.
I went over both RRs on the flight, and make some (significant) proposed changes. I attach the new version, where changes are shaded in yellow. Please take a look at your parts of both asap and let me know any comments. This was, of course, largely motivated by the recent realization that the very conservative values we put in the Supply Chain RR back when it was created are causing a float problem for the NSF scope. While those very conservative assumptions were sensible back then, when almost nothing in industry was working well and it was very hard to make any sensible predictions, clearly things have improved a lot by now. For example, we have seen no custom ASIC delays, and in fact received the PA/S and ADC preprod wafers earlier than scheduled. We are finding no significant delays in PCB fab either. There are still some delays for COTS components, but we can mitigate those by submitting the production orders early, using the "priming" scheme put in place by ATLAS. Given all these very encouraging signs, I propose significant changes to the Supply Chain RR. In addition, I propose also some adjustments to the main RR.

Let me know asap if you propose any changes to what I have put in the attached versions. We need to get these to Chris by early next week at the latest, so prompt attention would be greatly appreciated!

While writing, let me also say that next week is Spring Break at Columbia and I will be away on vacation Sunday-Friday. So unfortunately we will not be able to meet next Friday at our usual time. However, I will keep an eye on my email, so let me know of any things to discuss.

Thanks,
John

On 3/10/23 11:51 AM, John Parsons wrote:
Just landed at Newark. I spent time on the flight working on the RR and will send new version for checking later this afternoon

Sent from my iPhone

On Mar 10, 2023, at 10:36 AM, Ma, Hong <hma AT bnl.gov> wrote:



                As John is traveling back, we are not meeting today.

                There is a urgent request by PO to update the supply chain risks, which was discussed when we were preparing for the DR.

                Chris wants to run the MC next week.

                Please take a look at the latest risk registry,

https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196
<https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196>

and propose changes.

                The simplest is probably to drop the probability from 63% to a much lower level.

Please also note Gustaaf’s suggestion to increase the FW complexity risk cost.  I am not sure if I understand the logic, that adding resources will increase the cost when there is actually no new scope.

Best,

                Hong.

*From: *Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
*Date: *Friday, March 10, 2023 at 9:32 AM
*To: *Ma, Hong <hma AT bnl.gov>
*Cc: *Parsons, John <parsons AT nevis.columbia.edu>, Meyer, Chris <cjmey AT iu.edu>
*Subject: *Re: supply chain risks?

Hi Hong,

Those recommendation were made in  summer 2021 because we had no good basis at that time for individual estimates.  As you point out, we do now, so you should feel free to update the numbers.

BTW, looking at BCP 1058, the FW complexity risk maxed out at $150k, and we will now have added ~$1M in FW effort.  I would suggest to revise the upper value on that upward, as I think we are likely to have to add even more FW effort if we can find it.

Best,

Gustaaf



On Mar 10, 2023, at 3:03 PM, Ma, Hong <hma AT bnl.gov
<mailto:hma AT bnl.gov>> wrote:

Hi Gustaaf,

                I had an exchange with John after yesterday’s 2pm
meeting.    John is traveling today back to the US.

                We will not be able to provide the updated risks
by Monday noon, as Chris requested at the meeting, but we will try
to get it sometime next week.

                We will remove some of the risks (PA/Shaper
preproduction fabrication, for example), but there are still many
left with very high probabilities (63%), based on the
recommendation we had when the risks were first entered.

                Is there a new recommendation, or should we just
use our own judgement to update it?     The recent experience with
the vendors is not too bad, so some adjustment is warranted.

                Best,

                Hong.

*From:*Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu
<mailto:gusbroo AT nevis.columbia.edu>>
*Date:*Friday, March 10, 2023 at 7:25 AM
*To:*Parsons, John <parsons AT nevis.columbia.edu
<mailto:parsons AT nevis.columbia.edu>>, Ma, Hong <hma AT bnl.gov
<mailto:hma AT bnl.gov>>
*Cc:*Meyer, Chris <cjmey AT iu.edu <mailto:cjmey AT iu.edu>>
*Subject:*supply chain risks?


Hi John, Hong,

I think we’ll need your revised supply chain risks sometime next
week.  Is this possible?

Thx

Gustaaf

_______________________________________________
Usatlas-hllhc-lartl2l3-l mailing list
Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l

--
______________________________________________________________________

John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!CQNFPmdp4ryR1Wb_9lzndBPRZ5b8_45nRVlmC5T4wBS-jOYpHyZYsn8NhmYj79lfbgD-NWV8KKvE-cUdmo0D1MmbbYg-oFCyOwA5wTBZKVTtmg$


______________________________________________________________________

Attachment: Risk-Register_v76-2022-02-nsf-dr-JPmods.xlsx
Description: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet

Attachment: Risk-Register_Supply-Chain_v8-2022-02-nsf-dr-JPmods.xlsx
Description: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet




Archive powered by MHonArc 2.6.24.

Top of Page