usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "Ma, Hong" <hma AT bnl.gov>
- Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
- Date: Mon, 13 Mar 2023 17:44:04 -0500
Hi all,
Any more feedback on the modified RRs? I need to get them to Chris asap. I made proposed mods to all L3s, so I need everyone to check (both NSF and DOE).
Thanks,
John
On 3/11/23 6:57 PM, John Parsons wrote:
Hi Hong,
Good point! I will change that one back to the original 3-6 months.
BTW, during the steering mtg last week I asked Nicolas about the progress on the French robotic test system (since they did not make any presentation during LAr week). His reply was basically "progress is being made, but unfortunately not at the rate we hoped". He said they would hopefully be ready to start some initial testing with the system in "about 2 months". It sounded more like a hope than a plan. When I asked whether the plan is to then to build a second system to send to BNL, or just tell BNL the "recipe" for building their own, he said this had not been discussed yet. I came away even more pessimistic than before, and with the feeling that it will be months (probably at least 4, more likely more) before you could be operating such a system at BNL. I did not get a chance to talk with Gustaaf after the meeting, but I would expect he was also less than convinced. If you get a chance to raise the issue with the PO this week, hopefully they would be ready to move ahead with the feasibility study.
Regards,
John
On 3/11/23 2:52 PM, Ma, Hong wrote:
Hi John,
The changes are all very reasonable except we may want to hold off the change for PA/Shaper’s external dependency as we are still proposing to PO that we need to reduce that risk by looking for alternative robotic test.
Best,
Hong.
________________________________
From: John Parsons <parsons AT nevis.columbia.edu>
Sent: Friday, March 10, 2023 1:54 PM
To: Ma, Hong <hma AT bnl.gov>
Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
Hi all,
Just got back to NYC from a productive LAr week!
As Hong explained, we need to finalize SOON the two RRs (ie. the
"regular" one and the "supply chain" one), so that the MC can be run in
advance of freezing everything for the NSF rebaseline review.
I went over both RRs on the flight, and make some (significant)
proposed changes. I attach the new version, where changes are shaded in
yellow. Please take a look at your parts of both asap and let me know
any comments. This was, of course, largely motivated by the recent
realization that the very conservative values we put in the Supply Chain
RR back when it was created are causing a float problem for the NSF
scope. While those very conservative assumptions were sensible back
then, when almost nothing in industry was working well and it was very
hard to make any sensible predictions, clearly things have improved a
lot by now. For example, we have seen no custom ASIC delays, and in
fact received the PA/S and ADC preprod wafers earlier than scheduled.
We are finding no significant delays in PCB fab either. There are still
some delays for COTS components, but we can mitigate those by submitting
the production orders early, using the "priming" scheme put in place by
ATLAS. Given all these very encouraging signs, I propose significant
changes to the Supply Chain RR. In addition, I propose also some
adjustments to the main RR.
Let me know asap if you propose any changes to what I have put in the
attached versions. We need to get these to Chris by early next week at
the latest, so prompt attention would be greatly appreciated!
While writing, let me also say that next week is Spring Break at
Columbia and I will be away on vacation Sunday-Friday. So unfortunately
we will not be able to meet next Friday at our usual time. However, I
will keep an eye on my email, so let me know of any things to discuss.
Thanks,
John
On 3/10/23 11:51 AM, John Parsons wrote:
Just landed at Newark. I spent time on the flight working on the RR and
will send new version for checking later this afternoon
Sent from my iPhone
On Mar 10, 2023, at 10:36 AM, Ma, Hong <hma AT bnl.gov> wrote:
As John is traveling back, we are not meeting today.
There is a urgent request by PO to update the supply
chain risks, which was discussed when we were preparing for the DR.
Chris wants to run the MC next week.
Please take a look at the latest risk registry,
https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196
<https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196>
and propose changes.
The simplest is probably to drop the probability from
63% to a much lower level.
Please also note Gustaaf’s suggestion to increase the FW complexity
risk cost. I am not sure if I understand the logic, that adding
resources will increase the cost when there is actually no new scope.
Best,
Hong.
*From: *Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
*Date: *Friday, March 10, 2023 at 9:32 AM
*To: *Ma, Hong <hma AT bnl.gov>
*Cc: *Parsons, John <parsons AT nevis.columbia.edu>, Meyer, Chris
<cjmey AT iu.edu>
*Subject: *Re: supply chain risks?
Hi Hong,
Those recommendation were made in summer 2021 because we had no good
basis at that time for individual estimates. As you point out, we do
now, so you should feel free to update the numbers.
BTW, looking at BCP 1058, the FW complexity risk maxed out at $150k,
and we will now have added ~$1M in FW effort. I would suggest to
revise the upper value on that upward, as I think we are likely to
have to add even more FW effort if we can find it.
Best,
Gustaaf
On Mar 10, 2023, at 3:03 PM, Ma, Hong <hma AT bnl.gov
<mailto:hma AT bnl.gov>> wrote:
Hi Gustaaf,
I had an exchange with John after yesterday’s 2pm
meeting. John is traveling today back to the US.
We will not be able to provide the updated risks
by Monday noon, as Chris requested at the meeting, but we will try
to get it sometime next week.
We will remove some of the risks (PA/Shaper
preproduction fabrication, for example), but there are still many
left with very high probabilities (63%), based on the
recommendation we had when the risks were first entered.
Is there a new recommendation, or should we just
use our own judgement to update it? The recent experience with
the vendors is not too bad, so some adjustment is warranted.
Best,
Hong.
*From:*Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu
<mailto:gusbroo AT nevis.columbia.edu>>
*Date:*Friday, March 10, 2023 at 7:25 AM
*To:*Parsons, John <parsons AT nevis.columbia.edu
<mailto:parsons AT nevis.columbia.edu>>, Ma, Hong <hma AT bnl.gov
<mailto:hma AT bnl.gov>>
*Cc:*Meyer, Chris <cjmey AT iu.edu <mailto:cjmey AT iu.edu>>
*Subject:*supply chain risks?
Hi John, Hong,
I think we’ll need your revised supply chain risks sometime next
week. Is this possible?
Thx
Gustaaf
_______________________________________________
Usatlas-hllhc-lartl2l3-l mailing list
Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW: https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!B3TfNP6jTbYtvLDnsxsP559An5DDZw-RpPJyrkmPfbpprG8azL05DKYQGWM12xrh__-wh-2v2KgtciM_vVx0Ew$
______________________________________________________________________
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!GmUuAuFR5J2BYK0YCO0YAkjP9yr2w9g_ac7MbqSNAbIy6MLB-ZCKsg2oq6a3V1reaY-Vi7i9cu074n85v5PInFJatFxIhzl75M4rJRADxuzqqg$
______________________________________________________________________
-
[Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
Ma, Hong, 03/10/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/10/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/10/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
Ma, Hong, 03/11/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/11/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/13/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
Xu, Hao, 03/13/2023
- Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?, John Parsons, 03/13/2023
- Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?, Ma, Hong, 03/14/2023
- Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?, Tim Andeen, 03/14/2023
- Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?, John Parsons, 03/14/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
Xu, Hao, 03/13/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/13/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/11/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
Ma, Hong, 03/11/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/10/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/10/2023
Archive powered by MHonArc 2.6.24.