Skip to Content.
Sympa Menu

usatlas-hllhc-lartl2l3-l - Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: Tim Andeen <tandeen AT utexas.edu>
  • To: John Parsons <parsons AT nevis.columbia.edu>
  • Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
  • Date: Tue, 14 Mar 2023 09:45:13 -0700

Hi John, 

Sorry for the slow response (I took a long week for the start of our spring break). 

I this is probably already running, but just confirming that the changes for the optics and ADC look fine. 

One quick question that I’m pretty sure I know the answer to. This is the risk of SC delays with respect to the rebaselined schedule, correct? 

Best, Tim 



On Mar 13, 2023 at 9:01:23 PM, John Parsons <parsons AT nevis.columbia.edu> wrote:
Ok thx.

Sent from my iPhone

On Mar 13, 2023, at 8:18 PM, Xu, Hao <haoxu AT bnl.gov> wrote:

Thanks John. It  looks good to 6.4.4.


Regards,

Hao

________________________________
From: Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
Sent: Monday, March 13, 2023 6:44 PM
To: Ma, Hong <hma AT bnl.gov>
Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?


Hi all,

       Any more feedback on the modified RRs?  I need to get them to Chris
asap.  I made proposed mods to all L3s, so I need everyone to check
(both NSF and DOE).

       Thanks,
               John

> On 3/11/23 6:57 PM, John Parsons wrote:
>
> Hi Hong,
>
>     Good point!  I will change that one back to the original 3-6 months.
>     BTW, during the steering mtg last week I asked Nicolas about the
> progress on the French robotic test system (since they did not make any
> presentation during LAr week).  His reply was basically "progress is
> being made, but unfortunately not at the rate we hoped".  He said they
> would hopefully be ready to start some initial testing with the system
> in "about 2 months".  It sounded more like a hope than a plan.  When I
> asked whether the plan is to then to build a second system to send to
> BNL, or just tell BNL the "recipe" for building their own, he said this
> had not been discussed yet.  I came away even more pessimistic than
> before, and with the feeling that it will be months (probably at least
> 4, more likely more) before you could be operating such a system at BNL.
>  I did not get a chance to talk with Gustaaf after the meeting, but I
> would expect he was also less than convinced.  If you get a chance to
> raise the issue with the PO this week, hopefully they would be ready to
> move ahead with the feasibility study.
>     Regards,
>         John
>
>> On 3/11/23 2:52 PM, Ma, Hong wrote:
>> Hi John,
>>
>> The changes are all very reasonable except we may want to hold off the
>> change for PA/Shaper’s external dependency as we are still proposing
>> to PO that we need to reduce that risk by looking for alternative
>> robotic test.
>>
>>
>> Best,
>>
>> Hong.
>> ________________________________
>> From: John Parsons <parsons AT nevis.columbia.edu>
>> Sent: Friday, March 10, 2023 1:54 PM
>> To: Ma, Hong <hma AT bnl.gov>
>> Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
>> <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
>> Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
>>
>>
>> Hi all,
>>
>>         Just got back to NYC from a productive LAr week!
>>         As Hong explained, we need to finalize SOON the two RRs (ie. the
>> "regular" one and the "supply chain" one), so that the MC can be run in
>> advance of freezing everything for the NSF rebaseline review.
>>         I went over both RRs on the flight, and make some (significant)
>> proposed changes.  I attach the new version, where changes are shaded in
>> yellow.  Please take a look at your parts of both asap and let me know
>> any comments.  This was, of course, largely motivated by the recent
>> realization that the very conservative values we put in the Supply Chain
>> RR back when it was created are causing a float problem for the NSF
>> scope.  While those very conservative assumptions were sensible back
>> then, when almost nothing in industry was working well and it was very
>> hard to make any sensible predictions, clearly things have improved a
>> lot by now.  For example, we have seen no custom ASIC delays, and in
>> fact received the PA/S and ADC preprod wafers earlier than scheduled.
>> We are finding no significant delays in PCB fab either.  There are still
>> some delays for COTS components, but we can mitigate those by submitting
>> the production orders early, using the "priming" scheme put in place by
>> ATLAS.  Given all these very encouraging signs, I propose significant
>> changes to the Supply Chain RR.  In addition, I propose also some
>> adjustments to the main RR.
>>
>>         Let me know asap if you propose any changes to what I have
>> put in the
>> attached versions.  We need to get these to Chris by early next week at
>> the latest, so prompt attention would be greatly appreciated!
>>
>>         While writing, let me also say that next week is Spring Break at
>> Columbia and I will be away on vacation Sunday-Friday.  So unfortunately
>> we will not be able to meet next Friday at our usual time.  However, I
>> will keep an eye on my email, so let me know of any things to discuss.
>>
>>         Thanks,
>>                 John
>>
>> On 3/10/23 11:51 AM, John Parsons wrote:
>>> Just landed at Newark. I spent time on the flight working on the RR and
>>> will send new version for checking later this afternoon
>>>
>>> Sent from my iPhone
>>>
>>>> On Mar 10, 2023, at 10:36 AM, Ma, Hong <hma AT bnl.gov> wrote:
>>>>
>>>> 
>>>>
>>>>                 As John is traveling back, we are not meeting today.
>>>>
>>>>                 There is a urgent request by PO to update the supply
>>>> chain risks, which was discussed when we were preparing for the DR.
>>>>
>>>>                 Chris wants to run the MC next week.
>>>>
>>>>                 Please take a look at the latest risk registry,
>>>>
>>>> https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196 <https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196>
>>>>
>>>> and propose changes.
>>>>
>>>>                 The simplest is probably to drop the probability from
>>>> 63% to a much lower level.
>>>>
>>>> Please also note Gustaaf’s suggestion to increase the FW complexity
>>>> risk cost.  I am not sure if I understand the logic, that adding
>>>> resources will increase the cost when there is actually no new scope.
>>>>
>>>> Best,
>>>>
>>>>                 Hong.
>>>>
>>>> *From: *Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
>>>> *Date: *Friday, March 10, 2023 at 9:32 AM
>>>> *To: *Ma, Hong <hma AT bnl.gov>
>>>> *Cc: *Parsons, John <parsons AT nevis.columbia.edu>, Meyer, Chris
>>>> <cjmey AT iu.edu>
>>>> *Subject: *Re: supply chain risks?
>>>>
>>>> Hi Hong,
>>>>
>>>> Those recommendation were made in  summer 2021 because we had no good
>>>> basis at that time for individual estimates.  As you point out, we do
>>>> now, so you should feel free to update the numbers.
>>>>
>>>> BTW, looking at BCP 1058, the FW complexity risk maxed out at $150k,
>>>> and we will now have added ~$1M in FW effort.  I would suggest to
>>>> revise the upper value on that upward, as I think we are likely to
>>>> have to add even more FW effort if we can find it.
>>>>
>>>> Best,
>>>>
>>>> Gustaaf
>>>>
>>>>
>>>>
>>>>     On Mar 10, 2023, at 3:03 PM, Ma, Hong <hma AT bnl.gov
>>>>     <mailto:hma AT bnl.gov>> wrote:
>>>>
>>>>     Hi Gustaaf,
>>>>
>>>>                     I had an exchange with John after yesterday’s 2pm
>>>>     meeting.    John is traveling today back to the US.
>>>>
>>>>                     We will not be able to provide the updated risks
>>>>     by Monday noon, as Chris requested at the meeting, but we will try
>>>>     to get it sometime next week.
>>>>
>>>>                     We will remove some of the risks (PA/Shaper
>>>>     preproduction fabrication, for example), but there are still many
>>>>     left with very high probabilities (63%), based on the
>>>>     recommendation we had when the risks were first entered.
>>>>
>>>>                     Is there a new recommendation, or should we just
>>>>     use our own judgement to update it?     The recent experience with
>>>>     the vendors is not too bad, so some adjustment is warranted.
>>>>
>>>>                     Best,
>>>>
>>>>                     Hong.
>>>>
>>>>     *From:*Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu
>>>>     <mailto:gusbroo AT nevis.columbia.edu>>
>>>>     *Date:*Friday, March 10, 2023 at 7:25 AM
>>>>     *To:*Parsons, John <parsons AT nevis.columbia.edu
>>>>     <mailto:parsons AT nevis.columbia.edu>>, Ma, Hong <hma AT bnl.gov
>>>>     <mailto:hma AT bnl.gov>>
>>>>     *Cc:*Meyer, Chris <cjmey AT iu.edu <mailto:cjmey AT iu.edu>>
>>>>     *Subject:*supply chain risks?
>>>>
>>>>
>>>>     Hi John, Hong,
>>>>
>>>>     I think we’ll need your revised supply chain risks sometime next
>>>>     week.  Is this possible?
>>>>
>>>>     Thx
>>>>
>>>>     Gustaaf
>>>>
>>>> _______________________________________________
>>>> Usatlas-hllhc-lartl2l3-l mailing list
>>>> Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
>>>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l
>>
>> --
>> ______________________________________________________________________
>>
>> John Parsons
>> Nevis Labs,              Email: parsons AT nevis.columbia.edu
>>   Columbia University   Phone: (914) 591-2820
>> P.O. Box 137            Fax: (914) 591-8120
>> Irvington, NY 10533     WWW:
>> https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!B3TfNP6jTbYtvLDnsxsP559An5DDZw-RpPJyrkmPfbpprG8azL05DKYQGWM12xrh__-wh-2v2KgtciM_vVx0Ew$
>>
>> ______________________________________________________________________
>>
>

--
______________________________________________________________________

John Parsons
Nevis Labs,              Email: parsons AT nevis.columbia.edu
 Columbia University   Phone: (914) 591-2820
P.O. Box 137            Fax: (914) 591-8120
Irvington, NY 10533     WWW: https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!GmUuAuFR5J2BYK0YCO0YAkjP9yr2w9g_ac7MbqSNAbIy6MLB-ZCKsg2oq6a3V1reaY-Vi7i9cu074n85v5PInFJatFxIhzl75M4rJRADxuzqqg$

______________________________________________________________________
_______________________________________________
Usatlas-hllhc-lartl2l3-l mailing list
Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l


_______________________________________________
Usatlas-hllhc-lartl2l3-l mailing list
Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l



Archive powered by MHonArc 2.6.24.

Top of Page