| 
Hi John,                    You have retired the risk for ASIC pre-production packaging.  Will that be challenged, since we just submitted them for packaging and still a couple of months away from getting them back?
                   Best,                    Hong.      
From:
John Parsons <parsons AT nevis.columbia.edu>Date: Monday, March 13, 2023 at 10:01 PM
 To: Xu, Hao <haoxu AT bnl.gov>
 Cc: Ma, Hong <hma AT bnl.gov>, usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
 Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
 
Ok thx.
 Sent from my iPhone
 
 > On Mar 13, 2023, at 8:18 PM, Xu, Hao <haoxu AT bnl.gov> wrote:
 >
 > Thanks John. It  looks good to 6.4.4.
 >
 >
 > Regards,
 >
 > Hao
 >
 > ________________________________
 > From: Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
 > Sent: Monday, March 13, 2023 6:44 PM
 > To: Ma, Hong <hma AT bnl.gov>
 > Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
 > Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
 >
 >
 > Hi all,
 >
 >        Any more feedback on the modified RRs?  I need to get them to Chris
 > asap.  I made proposed mods to all L3s, so I need everyone to check
 > (both NSF and DOE).
 >
 >        Thanks,
 >                John
 >
 >> On 3/11/23 6:57 PM, John Parsons wrote:
 >>
 >> Hi Hong,
 >>
 >>     Good point!  I will change that one back to the original 3-6 months.
 >>     BTW, during the steering mtg last week I asked Nicolas about the
 >> progress on the French robotic test system (since they did not make any
 >> presentation during LAr week).  His reply was basically "progress is
 >> being made, but unfortunately not at the rate we hoped".  He said they
 >> would hopefully be ready to start some initial testing with the system
 >> in "about 2 months".  It sounded more like a hope than a plan.  When I
 >> asked whether the plan is to then to build a second system to send to
 >> BNL, or just tell BNL the "recipe" for building their own, he said this
 >> had not been discussed yet.  I came away even more pessimistic than
 >> before, and with the feeling that it will be months (probably at least
 >> 4, more likely more) before you could be operating such a system at BNL.
 >>  I did not get a chance to talk with Gustaaf after the meeting, but I
 >> would expect he was also less than convinced.  If you get a chance to
 >> raise the issue with the PO this week, hopefully they would be ready to
 >> move ahead with the feasibility study.
 >>     Regards,
 >>         John
 >>
 >>> On 3/11/23 2:52 PM, Ma, Hong wrote:
 >>> Hi John,
 >>>
 >>> The changes are all very reasonable except we may want to hold off the
 >>> change for PA/Shaper’s external dependency as we are still proposing
 >>> to PO that we need to reduce that risk by looking for alternative
 >>> robotic test.
 >>>
 >>>
 >>> Best,
 >>>
 >>> Hong.
 >>> ________________________________
 >>> From: John Parsons <parsons AT nevis.columbia.edu>
 >>> Sent: Friday, March 10, 2023 1:54 PM
 >>> To: Ma, Hong <hma AT bnl.gov>
 >>> Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
 >>> <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
 >>> Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
 >>>
 >>>
 >>> Hi all,
 >>>
 >>>         Just got back to NYC from a productive LAr week!
 >>>         As Hong explained, we need to finalize SOON the two RRs (ie. the
 >>> "regular" one and the "supply chain" one), so that the MC can be run in
 >>> advance of freezing everything for the NSF rebaseline review.
 >>>         I went over both RRs on the flight, and make some (significant)
 >>> proposed changes.  I attach the new version, where changes are shaded in
 >>> yellow.  Please take a look at your parts of both asap and let me know
 >>> any comments.  This was, of course, largely motivated by the recent
 >>> realization that the very conservative values we put in the Supply Chain
 >>> RR back when it was created are causing a float problem for the NSF
 >>> scope.  While those very conservative assumptions were sensible back
 >>> then, when almost nothing in industry was working well and it was very
 >>> hard to make any sensible predictions, clearly things have improved a
 >>> lot by now.  For example, we have seen no custom ASIC delays, and in
 >>> fact received the PA/S and ADC preprod wafers earlier than scheduled.
 >>> We are finding no significant delays in PCB fab either.  There are still
 >>> some delays for COTS components, but we can mitigate those by submitting
 >>> the production orders early, using the "priming" scheme put in place by
 >>> ATLAS.  Given all these very encouraging signs, I propose significant
 >>> changes to the Supply Chain RR.  In addition, I propose also some
 >>> adjustments to the main RR.
 >>>
 >>>         Let me know asap if you propose any changes to what I have
 >>> put in the
 >>> attached versions.  We need to get these to Chris by early next week at
 >>> the latest, so prompt attention would be greatly appreciated!
 >>>
 >>>         While writing, let me also say that next week is Spring Break at
 >>> Columbia and I will be away on vacation Sunday-Friday.  So unfortunately
 >>> we will not be able to meet next Friday at our usual time.  However, I
 >>> will keep an eye on my email, so let me know of any things to discuss.
 >>>
 >>>         Thanks,
 >>>                 John
 >>>
 >>> On 3/10/23 11:51 AM, John Parsons wrote:
 >>>> Just landed at Newark. I spent time on the flight working on the RR and
 >>>> will send new version for checking later this afternoon
 >>>>
 >>>> Sent from my iPhone
 >>>>
 >>>>> On Mar 10, 2023, at 10:36 AM, Ma, Hong <hma AT bnl.gov> wrote:
 >>>>>
 >>>>> 
 >>>>>
 >>>>>                 As John is traveling back, we are not meeting today.
 >>>>>
 >>>>>                 There is a urgent request by PO to update the supply
 >>>>> chain risks, which was discussed when we were preparing for the DR.
 >>>>>
 >>>>>                 Chris wants to run the MC next week.
 >>>>>
 >>>>>                 Please take a look at the latest risk registry,
 >>>>>
 >>>>> 
https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196 <https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196>
 >>>>>
 >>>>> and propose changes.
 >>>>>
 >>>>>                 The simplest is probably to drop the probability from
 >>>>> 63% to a much lower level.
 >>>>>
 >>>>> Please also note Gustaaf’s suggestion to increase the FW complexity
 >>>>> risk cost.  I am not sure if I understand the logic, that adding
 >>>>> resources will increase the cost when there is actually no new scope.
 >>>>>
 >>>>> Best,
 >>>>>
 >>>>>                 Hong.
 >>>>>
 >>>>> *From: *Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
 >>>>> *Date: *Friday, March 10, 2023 at 9:32 AM
 >>>>> *To: *Ma, Hong <hma AT bnl.gov>
 >>>>> *Cc: *Parsons, John <parsons AT nevis.columbia.edu>, Meyer, Chris
 >>>>> <cjmey AT iu.edu>
 >>>>> *Subject: *Re: supply chain risks?
 >>>>>
 >>>>> Hi Hong,
 >>>>>
 >>>>> Those recommendation were made in  summer 2021 because we had no good
 >>>>> basis at that time for individual estimates.  As you point out, we do
 >>>>> now, so you should feel free to update the numbers.
 >>>>>
 >>>>> BTW, looking at BCP 1058, the FW complexity risk maxed out at $150k,
 >>>>> and we will now have added ~$1M in FW effort.  I would suggest to
 >>>>> revise the upper value on that upward, as I think we are likely to
 >>>>> have to add even more FW effort if we can find it.
 >>>>>
 >>>>> Best,
 >>>>>
 >>>>> Gustaaf
 >>>>>
 >>>>>
 >>>>>
 >>>>>     On Mar 10, 2023, at 3:03 PM, Ma, Hong <hma AT bnl.gov
 >>>>>     <mailto:hma AT bnl.gov>> wrote:
 >>>>>
 >>>>>     Hi Gustaaf,
 >>>>>
 >>>>>                     I had an exchange with John after yesterday’s 2pm
 >>>>>     meeting.    John is traveling today back to the US.
 >>>>>
 >>>>>                     We will not be able to provide the updated risks
 >>>>>     by Monday noon, as Chris requested at the meeting, but we will try
 >>>>>     to get it sometime next week.
 >>>>>
 >>>>>                     We will remove some of the risks (PA/Shaper
 >>>>>     preproduction fabrication, for example), but there are still many
 >>>>>     left with very high probabilities (63%), based on the
 >>>>>     recommendation we had when the risks were first entered.
 >>>>>
 >>>>>                     Is there a new recommendation, or should we just
 >>>>>     use our own judgement to update it?     The recent experience with
 >>>>>     the vendors is not too bad, so some adjustment is warranted.
 >>>>>
 >>>>>                     Best,
 >>>>>
 >>>>>                     Hong.
 >>>>>
 >>>>>     *From:*Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu
 >>>>>     <mailto:gusbroo AT nevis.columbia.edu>>
 >>>>>     *Date:*Friday, March 10, 2023 at 7:25 AM
 >>>>>     *To:*Parsons, John <parsons AT nevis.columbia.edu
 >>>>>     <mailto:parsons AT nevis.columbia.edu>>, Ma, Hong <hma AT bnl.gov
 >>>>>     <mailto:hma AT bnl.gov>>
 >>>>>     *Cc:*Meyer, Chris <cjmey AT iu.edu <mailto:cjmey AT iu.edu>>
 >>>>>     *Subject:*supply chain risks?
 >>>>>
 >>>>>
 >>>>>     Hi John, Hong,
 >>>>>
 >>>>>     I think we’ll need your revised supply chain risks sometime next
 >>>>>     week.  Is this possible?
 >>>>>
 >>>>>     Thx
 >>>>>
 >>>>>     Gustaaf
 >>>>>
 >>>>> _______________________________________________
 >>>>> Usatlas-hllhc-lartl2l3-l mailing list
 >>>>> Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
 >>>>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l
 >>>
 >>> --
 >>> ______________________________________________________________________
 >>>
 >>> John Parsons
 >>> Nevis Labs,              Email: parsons AT nevis.columbia.edu
 >>>   Columbia University   Phone: (914) 591-2820
 >>> P.O. Box 137            Fax: (914) 591-8120
 >>> Irvington, NY 10533     WWW:
 >>> 
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!B3TfNP6jTbYtvLDnsxsP559An5DDZw-RpPJyrkmPfbpprG8azL05DKYQGWM12xrh__-wh-2v2KgtciM_vVx0Ew$
 >>>
 >>> ______________________________________________________________________
 >>>
 >>
 >
 > --
 > ______________________________________________________________________
 >
 > John Parsons
 > Nevis Labs,              Email: parsons AT nevis.columbia.edu
 >  Columbia University   Phone: (914) 591-2820
 > P.O. Box 137            Fax: (914) 591-8120
 > Irvington, NY 10533     WWW: 
https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!GmUuAuFR5J2BYK0YCO0YAkjP9yr2w9g_ac7MbqSNAbIy6MLB-ZCKsg2oq6a3V1reaY-Vi7i9cu074n85v5PInFJatFxIhzl75M4rJRADxuzqqg$
 >
 > ______________________________________________________________________
 > _______________________________________________
 > Usatlas-hllhc-lartl2l3-l mailing list
 > Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
 > https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l
 >
 |