usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List
List archive
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
- From: "Xu, Hao" <haoxu AT bnl.gov>
- To: "Parsons, John" <parsons AT nevis.columbia.edu>, "Ma, Hong" <hma AT bnl.gov>
- Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
- Date: Tue, 14 Mar 2023 01:17:56 +0000
Thanks John. It looks good to 6.4.4.
Regards,
Hao
From: Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> on behalf of John Parsons <parsons AT nevis.columbia.edu>
Sent: Monday, March 13, 2023 6:44 PM
To: Ma, Hong <hma AT bnl.gov>
Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
Sent: Monday, March 13, 2023 6:44 PM
To: Ma, Hong <hma AT bnl.gov>
Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
Hi all,
Any more feedback on the modified RRs? I need to get them to Chris
asap. I made proposed mods to all L3s, so I need everyone to check
(both NSF and DOE).
Thanks,
John
On 3/11/23 6:57 PM, John Parsons wrote:
>
> Hi Hong,
>
> Good point! I will change that one back to the original 3-6 months.
> BTW, during the steering mtg last week I asked Nicolas about the
> progress on the French robotic test system (since they did not make any
> presentation during LAr week). His reply was basically "progress is
> being made, but unfortunately not at the rate we hoped". He said they
> would hopefully be ready to start some initial testing with the system
> in "about 2 months". It sounded more like a hope than a plan. When I
> asked whether the plan is to then to build a second system to send to
> BNL, or just tell BNL the "recipe" for building their own, he said this
> had not been discussed yet. I came away even more pessimistic than
> before, and with the feeling that it will be months (probably at least
> 4, more likely more) before you could be operating such a system at BNL.
> I did not get a chance to talk with Gustaaf after the meeting, but I
> would expect he was also less than convinced. If you get a chance to
> raise the issue with the PO this week, hopefully they would be ready to
> move ahead with the feasibility study.
> Regards,
> John
>
> On 3/11/23 2:52 PM, Ma, Hong wrote:
>> Hi John,
>>
>> The changes are all very reasonable except we may want to hold off the
>> change for PA/Shaper’s external dependency as we are still proposing
>> to PO that we need to reduce that risk by looking for alternative
>> robotic test.
>>
>>
>> Best,
>>
>> Hong.
>> ________________________________
>> From: John Parsons <parsons AT nevis.columbia.edu>
>> Sent: Friday, March 10, 2023 1:54 PM
>> To: Ma, Hong <hma AT bnl.gov>
>> Cc: usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
>> <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
>> Subject: Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?
>>
>>
>> Hi all,
>>
>> Just got back to NYC from a productive LAr week!
>> As Hong explained, we need to finalize SOON the two RRs (ie. the
>> "regular" one and the "supply chain" one), so that the MC can be run in
>> advance of freezing everything for the NSF rebaseline review.
>> I went over both RRs on the flight, and make some (significant)
>> proposed changes. I attach the new version, where changes are shaded in
>> yellow. Please take a look at your parts of both asap and let me know
>> any comments. This was, of course, largely motivated by the recent
>> realization that the very conservative values we put in the Supply Chain
>> RR back when it was created are causing a float problem for the NSF
>> scope. While those very conservative assumptions were sensible back
>> then, when almost nothing in industry was working well and it was very
>> hard to make any sensible predictions, clearly things have improved a
>> lot by now. For example, we have seen no custom ASIC delays, and in
>> fact received the PA/S and ADC preprod wafers earlier than scheduled.
>> We are finding no significant delays in PCB fab either. There are still
>> some delays for COTS components, but we can mitigate those by submitting
>> the production orders early, using the "priming" scheme put in place by
>> ATLAS. Given all these very encouraging signs, I propose significant
>> changes to the Supply Chain RR. In addition, I propose also some
>> adjustments to the main RR.
>>
>> Let me know asap if you propose any changes to what I have
>> put in the
>> attached versions. We need to get these to Chris by early next week at
>> the latest, so prompt attention would be greatly appreciated!
>>
>> While writing, let me also say that next week is Spring Break at
>> Columbia and I will be away on vacation Sunday-Friday. So unfortunately
>> we will not be able to meet next Friday at our usual time. However, I
>> will keep an eye on my email, so let me know of any things to discuss.
>>
>> Thanks,
>> John
>>
>> On 3/10/23 11:51 AM, John Parsons wrote:
>>> Just landed at Newark. I spent time on the flight working on the RR and
>>> will send new version for checking later this afternoon
>>>
>>> Sent from my iPhone
>>>
>>>> On Mar 10, 2023, at 10:36 AM, Ma, Hong <hma AT bnl.gov> wrote:
>>>>
>>>>
>>>>
>>>> As John is traveling back, we are not meeting today.
>>>>
>>>> There is a urgent request by PO to update the supply
>>>> chain risks, which was discussed when we were preparing for the DR.
>>>>
>>>> Chris wants to run the MC next week.
>>>>
>>>> Please take a look at the latest risk registry,
>>>>
>>>> https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196 <https://atlas-hllhc.docdb.bnl.gov/cgi-bin/public/ShowDocument?docid=196>
>>>>
>>>> and propose changes.
>>>>
>>>> The simplest is probably to drop the probability from
>>>> 63% to a much lower level.
>>>>
>>>> Please also note Gustaaf’s suggestion to increase the FW complexity
>>>> risk cost. I am not sure if I understand the logic, that adding
>>>> resources will increase the cost when there is actually no new scope.
>>>>
>>>> Best,
>>>>
>>>> Hong.
>>>>
>>>> *From: *Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu>
>>>> *Date: *Friday, March 10, 2023 at 9:32 AM
>>>> *To: *Ma, Hong <hma AT bnl.gov>
>>>> *Cc: *Parsons, John <parsons AT nevis.columbia.edu>, Meyer, Chris
>>>> <cjmey AT iu.edu>
>>>> *Subject: *Re: supply chain risks?
>>>>
>>>> Hi Hong,
>>>>
>>>> Those recommendation were made in summer 2021 because we had no good
>>>> basis at that time for individual estimates. As you point out, we do
>>>> now, so you should feel free to update the numbers.
>>>>
>>>> BTW, looking at BCP 1058, the FW complexity risk maxed out at $150k,
>>>> and we will now have added ~$1M in FW effort. I would suggest to
>>>> revise the upper value on that upward, as I think we are likely to
>>>> have to add even more FW effort if we can find it.
>>>>
>>>> Best,
>>>>
>>>> Gustaaf
>>>>
>>>>
>>>>
>>>> On Mar 10, 2023, at 3:03 PM, Ma, Hong <hma AT bnl.gov
>>>> <mailto:hma AT bnl.gov>> wrote:
>>>>
>>>> Hi Gustaaf,
>>>>
>>>> I had an exchange with John after yesterday’s 2pm
>>>> meeting. John is traveling today back to the US.
>>>>
>>>> We will not be able to provide the updated risks
>>>> by Monday noon, as Chris requested at the meeting, but we will try
>>>> to get it sometime next week.
>>>>
>>>> We will remove some of the risks (PA/Shaper
>>>> preproduction fabrication, for example), but there are still many
>>>> left with very high probabilities (63%), based on the
>>>> recommendation we had when the risks were first entered.
>>>>
>>>> Is there a new recommendation, or should we just
>>>> use our own judgement to update it? The recent experience with
>>>> the vendors is not too bad, so some adjustment is warranted.
>>>>
>>>> Best,
>>>>
>>>> Hong.
>>>>
>>>> *From:*Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu
>>>> <mailto:gusbroo AT nevis.columbia.edu>>
>>>> *Date:*Friday, March 10, 2023 at 7:25 AM
>>>> *To:*Parsons, John <parsons AT nevis.columbia.edu
>>>> <mailto:parsons AT nevis.columbia.edu>>, Ma, Hong <hma AT bnl.gov
>>>> <mailto:hma AT bnl.gov>>
>>>> *Cc:*Meyer, Chris <cjmey AT iu.edu <mailto:cjmey AT iu.edu>>
>>>> *Subject:*supply chain risks?
>>>>
>>>>
>>>> Hi John, Hong,
>>>>
>>>> I think we’ll need your revised supply chain risks sometime next
>>>> week. Is this possible?
>>>>
>>>> Thx
>>>>
>>>> Gustaaf
>>>>
>>>> _______________________________________________
>>>> Usatlas-hllhc-lartl2l3-l mailing list
>>>> Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
>>>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l
>>
>> --
>> ______________________________________________________________________
>>
>> John Parsons
>> Nevis Labs, Email: parsons AT nevis.columbia.edu
>> Columbia University Phone: (914) 591-2820
>> P.O. Box 137 Fax: (914) 591-8120
>> Irvington, NY 10533 WWW:
>> https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!B3TfNP6jTbYtvLDnsxsP559An5DDZw-RpPJyrkmPfbpprG8azL05DKYQGWM12xrh__-wh-2v2KgtciM_vVx0Ew$
>>
>> ______________________________________________________________________
>>
>
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW: https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!GmUuAuFR5J2BYK0YCO0YAkjP9yr2w9g_ac7MbqSNAbIy6MLB-ZCKsg2oq6a3V1reaY-Vi7i9cu074n85v5PInFJatFxIhzl75M4rJRADxuzqqg$
______________________________________________________________________
_______________________________________________
Usatlas-hllhc-lartl2l3-l mailing list
Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l
-
[Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
Ma, Hong, 03/10/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/10/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/10/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
Ma, Hong, 03/11/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/11/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/13/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
Xu, Hao, 03/13/2023
- Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?, John Parsons, 03/13/2023
- Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?, Ma, Hong, 03/14/2023
- Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?, Tim Andeen, 03/14/2023
- Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?, John Parsons, 03/14/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
Xu, Hao, 03/13/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/13/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/11/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
Ma, Hong, 03/11/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/10/2023
-
Re: [Usatlas-hllhc-lartl2l3-l] FW: supply chain risks?,
John Parsons, 03/10/2023
Archive powered by MHonArc 2.6.24.