usatlas-hllhc-lartl2l3-l - Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks

usatlas-hllhc-lartl2l3-l AT lists.bnl.gov

Subject: U.S. ATLAS HL-LHC Upgrade LAr Level 2 and Level 3 Managers Mailing List

List archive

Chronological Thread  
  • From: Andy Haas <andy.haas AT nyu.edu>
  • To: John Parsons <parsons AT nevis.columbia.edu>
  • Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
  • Subject: Re: [Usatlas-hllhc-lartl2l3-l] delay table for L3 talks
  • Date: Mon, 3 Apr 2023 10:26:26 -0600

Nevermind, I see. We collect these from the ContingencyTracking
spreadsheet on the agenda page.

On Mon, Apr 3, 2023 at 10:16 AM Andy Haas <andy.haas AT nyu.edu> wrote:
>
> OK for slide 7.
> But where do we get info for slide 6 - BCPs? Did you already dig these up?
>
> On Sat, Apr 1, 2023 at 1:10 PM John Parsons <parsons AT nevis.columbia.edu>
> wrote:
> >
> >
> > Hi all,
> >
> > As we discussed, I have gone through the various BCPs and
> > produced a
> > table summarizing the delays for each L3. I have put this new table in
> > the draft of my FEB2 "Cost&Schedule" slides, and uploaded them to
> > yesterday's Indico
> > (https://urldefense.proofpoint.com/v2/url?u=https-3A__indico.bnl.gov_event_18946_&d=DwICAg&c=slrrB7dE8n7gBJbeO0g-IQ&r=y4qQBOsjsdgJNx-_8SvpS9786vHE4GOddPXp1ozJgWc&m=7ubE_D9VZaFJOdv8oN2ShyAGYKlhSdLcNS0yRMgk-FvxunP974B6DGlyddU7IwfC&s=Dtyyi7HZ5rw-EkJm4ONSeus6tcM5_90280W3qCS_ljw&e=
> > ). The table is
> > all I have done so far on those new slides so far, and it is on p. 7 of
> > those slides; Tim and Andy should put a similar slide with a copy of the
> > same table in their L3 Cost&Schedule slides.
> > As additional info, here are the milestones I used to quantify the
> > delays at L3, and their respective dates currently and at the start of
> > the MREFC:
> >
> > 6.4.1
> > FEE20940 (Milestone: ADC Production Complete)
> > Current date: 24-Jun-25
> > MREFC start date: 9-Jan-24
> >
> > 6.4.3
> > BEE11060 (Milestone: BE Acceptance Test Complete)
> > Current date: 30-Sep-26
> > MREFC start date: 3-Jan-25
> >
> > Regards,
> > John
> > --
> > ______________________________________________________________________
> >
> > John Parsons
> > Nevis Labs, Email: parsons AT nevis.columbia.edu
> > Columbia University Phone: (914) 591-2820
> > P.O. Box 137 Fax: (914) 591-8120
> > Irvington, NY 10533 WWW:
> > https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!FV51tfDSbKev3_E3ZAMJpVMgPOkM9ur-Hg1Z5AKoKJoH1AnlZSVcf9cbVu7rUBpVzqXsyTY93vCoQc3bc6ChZMUKbYXK21ZpZhQmvo0WzmYfwA$
> >
> > ______________________________________________________________________
> > _______________________________________________
> > Usatlas-hllhc-lartl2l3-l mailing list
> > Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
> > https://urldefense.proofpoint.com/v2/url?u=https-3A__lists.bnl.gov_mailman_listinfo_usatlas-2Dhllhc-2Dlartl2l3-2Dl&d=DwICAg&c=slrrB7dE8n7gBJbeO0g-IQ&r=y4qQBOsjsdgJNx-_8SvpS9786vHE4GOddPXp1ozJgWc&m=7ubE_D9VZaFJOdv8oN2ShyAGYKlhSdLcNS0yRMgk-FvxunP974B6DGlyddU7IwfC&s=z2_j6YO3TG3yYtnoLjVkV5Mz8j0dnHnj-sQQTPvS9JQ&e=