star-fst-l AT lists.bnl.gov
Subject: Star-fst-l mailing list
List archive
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time)
- From: "Capotosto, Michael" <capotosto AT bnl.gov>
- To: "Videbaek, Flemming" <videbaek AT bnl.gov>, Gerard Visser <gvisser AT indiana.edu>
- Cc: "star-fst-l AT lists.bnl.gov" <star-fst-l AT lists.bnl.gov>
- Subject: Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time)
- Date: Wed, 12 Aug 2020 12:43:53 +0000
Hey Gerard, All,
If you're trying to find emails regarding this, it looks like Steve had me
make the modifications in April or May of 2019.
When I did the modification I cut *and lifted* a section of track for OUT8P
and OUT8N between those .1" pitch pads and the 50 pos d-sub - so we can't
just bridge it, we'd have to scrape the mask off and lay two pieces of magnet
wire in. It'd be rather labor intensive and time consuming to bring the PPB
back to original.
I'd propose a simpler solution:
1. We can remove the 28AWG jumpers installed in this picture
https://drupal.star.bnl.gov/STAR/system/files/FST%20Modifications%20to%20IST%20Patch%20Panel%20Board_4APR19.png
2. We bridge OUT8P and OUT10P, OUT8N and OUT10N on the PPB (8 and 10
are adjacent, according to the silkscreen. They are a 0.1" pitch, so we can
very easily bridge with a 1206 0R resistor)
3. We make the modifications to the ABC board, using OUT10P/OUT10N
for the second bias voltage.
Other than this, I'll get a quote or two for the current ABC boards, that
should give us an idea of what it would cost if we wanted to do a respin with
the added BNCs. I'll think about how best we can add the BNC pigtails as
well.
--Mike
-----Original Message-----
From: Star-fst-l <star-fst-l-bounces AT lists.bnl.gov> On Behalf Of videbaek
Sent: Tuesday, August 11, 2020 4:41 PM
To: Gerard Visser <gvisser AT indiana.edu>
Cc: star-fst-l AT lists.bnl.gov
Subject: Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time)
Hi Gerard,
thanks for your input. I just want to remind all that we have a plan for
checking out the full chain with the system in November or so connecting to
DAQ. We should take this opportunity to have mods done for a few boards so we
can run and exercise a (test) module in the Hall.
best F.
On 2020-08-11 16:34, Gerard Visser wrote:
> hi Zhenyu & all,
> I looked at all out schematics concerning the bias voltage
> connections and things should work out very well. We have to un-do the
> changes that we unfortunately made to all the PPB, which was not wise
> to have done before we had a final plan. But it should be feasible.
> And then we have to modify the ABC boards (18 of them) to cut two of
> the signal pairs from the ARM connector and instead wire to two new
> BNC conenctors (or to two cable pigtails to BNC connectors, would be
> OK). It would be possible to build 18 new ABC boards instead, but the
> D connectors if we use same high quality ones are rather expensive.
> Mike should please consider the pro/con for modification vs. new ABC
> boards.
> Attached slides summarize the detector bias connections from the
> detectors to the BNC connectors. Mike please check that I didn't get
> something wrong, of course.
> Let's call this decided, and get the PPB's back to their original
> state, and modify one or a few of the ABC boards for the test
> setup(s).
> Sincerely,
>
> Gerard
>
> p.s. We should hi-pot the bias connections (up to T-board, unplugged
> from the hybrids) to some test voltage that makes sense (TBD) based on
> maximum operating voltage you expect. What is that max operating
> voltage?
>
>
> On 8/10/2020 1:25 PM, Ye, Zhenyu wrote:
>> Minutes:
>>
>> 1. Flemming showed a draft of committee recommendations. He will have
>> a meeting with the committee this afternoon. Expect to have a final
>> version soon.
>>
>> 2. Silicon sensors
>> -> Zhenyu: requested for a new quote from Hamamatsu. Partial delivery
>> of Silicon sensors is not possible.
>>
>> 3. Use thermal camera with cooling applied to the other side of the
>> mechanical structure to check if there is air trapped between hybrid
>> and MS
>> -> Yi: trying it this week. Consider doing this in production
>>
>> 4. Update the T-board design
>> -> Jianing will update the design this week
>> 1) Move the capacitor to the other side
>> 2) Add two ground holes
>> 3) Tolerance for mounting T-board on the MS, taking into account the
>> constraint from connecting the outer hybrid
>> 4) Check mounting T-board on the MS -> Yi will do it at NCKU
>>
>> 5. Split HV for inner and outer
>> -> Decided to split HV. Mike/Gerard will look into the changes to PPB
>> and back-of-crate boards
>>
>> 6. Integration
>> -> Rahul: will do a tolerance analysis, taking into account the
>> clearance/project requirements but also what can be achieved by the
>> machine shop. Need to have a plan for survey and discuss with Survey
>> group
>>
>> 7. Simulation
>> -> Gavin/Shenghui: slow simulator based on cosmic data is ready.
>> Trying to run the tracking code on RCF.
>>
>> 8. Mechanical structure
>> -> Yi: Han-Sheng leaving the project next week for PhD in US. Test
>> the new procedure with old hybrids. Will verify with the vendor about
>> changes to the precision pin: lead and pin lengths
>>
>> ***** Action items *****
>> 1) Design and fabricate light-tight box for the DAQ integration test
>> at BNL - Rahul/Flemming
>> 2) Design the cooling lines, and cable trays between disks and
>> cooling manifold - Felix/Rahul
>> 3) Finalize how to mount modules onto the half-rings, and half-rings
>> onto support structure, and document the proposed changes to the
>> mechanical structure - Rahul/Yi/Zhenyu
>> 4) Survey procedure/requirements - Rahul
>>
>> 5) Prepare documents for prelim Safety review with C-AD - all
>> 6) Get updated quote from Hamamatsu - Zhenyu
>> 7) Design and fabricate module storage boxes for production at UIC -
>> Xu/Andres
>> 8) Duplicate the module assembly tooling at UIC - Xu/Zhenyu
>> 9) Discuss with Fermilab about module assembly schedule - Zhenyu
>>
>> 10) Update the T-board design to avoid the conflict with Mechanical
>> structure - Jianing/Maowu
>> 11) Check how T-board mount onto MS - Yi
>>
>> 12) Look into splitting the inner and outer sensor HV bias -
>> Mike/Gerard
>> 13) Send the problematic prototype cable-T-board assembly to Mike for
>> investigation - Zhenyu/Mike
>> 14) Develop the QC procedure for Inner cable and T-board assembly -
>> Mike/Maowu
>>
>> 15) Look into the overall large CMN noise, and the abnormal noise of
>> few channels first appear in the readout - Gerard/Xu
>> 16) Check the FST noise performance at high readout rate - Xu/Zhenyu
>> 17) Sett up the laser test stand to characterize prototype module
>> performance - Andres/Zhenyu
>> 18) FST slow simulator with efficiency/resolution measured with
>> prototypes and study tracking performance - Gavin/Shenghui
>>
>>> On Aug 8, 2020, at 10:48 AM, Ye, Zhenyu <yezhenyu AT uic.edu> wrote:
>>>
>>> Dear all,
>>>
>>> We will have the Weekly FST meeting on Monday starting at 9am EST
>>> (BNL local time).
>>>
>>> Bluejeans Meeting URL https://bluejeans.com/101020434 Meeting ID:
>>> 101 020 434
>>>
>>> https://drupal.star.bnl.gov/STAR/event/2020/08/10/star-forward-silic
>>> on-tracker-meeting
>>>
>>> 0. follow-ups on review and action items
>>> 1. Integration
>>> by Rahul Sharma, Felix Archampong
>>> 2. Hybrid and T-board
>>> by Maowu Nie, Jianing Dong
>>> 3. Simulation Studies
>>> by Gavin Wilks, Shenghui Zhang, Daniel Brandenburg
>>> 4. Prototype Module Assembly and Test by Zhenyu
>>> Ye
>>> 5. Mechanical structure
>>> by Yi Yang
>>> _______________________________________________
>>> Star-fst-l mailing list
>>> Star-fst-l AT lists.bnl.gov
>>> https://lists.bnl.gov/mailman/listinfo/star-fst-l
>>
>> _______________________________________________
>> Star-fst-l mailing list
>> Star-fst-l AT lists.bnl.gov
>> https://lists.bnl.gov/mailman/listinfo/star-fst-l
>>
>
> _______________________________________________
> Star-fst-l mailing list
> Star-fst-l AT lists.bnl.gov
> https://lists.bnl.gov/mailman/listinfo/star-fst-l
--
Flemming Videbaek
senior scientist
videbaek @ bnl.gov
Brookhaven National Lab
Physics Department
Bldg 510D
Upton, NY 11973
phone: 631-344-4106
cell : 631-681-1596
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time)
, (continued)
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Yi Yang, 08/10/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Yi Yang, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/12/2020
- Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time), Yi Yang, 08/12/2020
- Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time), videbaek, 08/12/2020
- Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time), Gerard Visser, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Yi Yang, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Yi Yang, 08/10/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
videbaek, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Capotosto, Michael, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/12/2020
- Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time), Zhenyu Ye, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Capotosto, Michael, 08/12/2020
Archive powered by MHonArc 2.6.24.