hi Zhenyu & all,
I looked at all out schematics concerning the bias voltage connections and things should work out very well. We have to un-do the changes that we unfortunately made to all the PPB, which was not wise to have done before we had a final plan. But it should be feasible. And then we have to modify the ABC boards (18 of them) to cut two of the signal pairs from the ARM connector and instead wire to two new BNC conenctors (or to two cable pigtails to BNC connectors, would be OK). It would be possible to build 18 new ABC boards instead, but the D connectors if we use same high quality ones are rather expensive. Mike should please consider the pro/con for modification vs. new ABC boards.
Attached slides summarize the detector bias connections from the detectors to the BNC connectors. Mike please check that I didn't get something wrong, of course.
Let's call this decided, and get the PPB's back to their original state, and modify one or a few of the ABC boards for the test setup(s).
Sincerely,
Gerard
p.s. We should hi-pot the bias connections (up to T-board, unplugged from the hybrids) to some test voltage that makes sense (TBD) based on maximum operating voltage you expect. What is that max operating voltage?
On 8/10/2020 1:25 PM, Ye, Zhenyu wrote:
Minutes:
1. Flemming showed a draft of committee recommendations. He will have a
meeting with the committee this afternoon. Expect to have a final version
soon.
2. Silicon sensors
-> Zhenyu: requested for a new quote from Hamamatsu. Partial delivery of
Silicon sensors is not possible.
3. Use thermal camera with cooling applied to the other side of the
mechanical structure to check if there is air trapped between hybrid and MS
-> Yi: trying it this week. Consider doing this in production
4. Update the T-board design
-> Jianing will update the design this week
1) Move the capacitor to the other side
2) Add two ground holes
3) Tolerance for mounting T-board on the MS, taking into account the
constraint from connecting the outer hybrid
4) Check mounting T-board on the MS -> Yi will do it at NCKU
5. Split HV for inner and outer
-> Decided to split HV. Mike/Gerard will look into the changes to PPB and
back-of-crate boards
6. Integration
-> Rahul: will do a tolerance analysis, taking into account the
clearance/project requirements but also what can be achieved by the machine
shop. Need to have a plan for survey and discuss with Survey group
7. Simulation
-> Gavin/Shenghui: slow simulator based on cosmic data is ready. Trying to
run the tracking code on RCF.
8. Mechanical structure
-> Yi: Han-Sheng leaving the project next week for PhD in US. Test the new
procedure with old hybrids. Will verify with the vendor about changes to the
precision pin: lead and pin lengths
***** Action items *****
1) Design and fabricate light-tight box for the DAQ integration test at BNL -
Rahul/Flemming
2) Design the cooling lines, and cable trays between disks and cooling
manifold - Felix/Rahul
3) Finalize how to mount modules onto the half-rings, and half-rings onto
support structure, and document the proposed changes to the mechanical
structure - Rahul/Yi/Zhenyu
4) Survey procedure/requirements - Rahul
5) Prepare documents for prelim Safety review with C-AD - all
6) Get updated quote from Hamamatsu - Zhenyu
7) Design and fabricate module storage boxes for production at UIC - Xu/Andres
8) Duplicate the module assembly tooling at UIC - Xu/Zhenyu
9) Discuss with Fermilab about module assembly schedule - Zhenyu
10) Update the T-board design to avoid the conflict with Mechanical structure
- Jianing/Maowu
11) Check how T-board mount onto MS - Yi
12) Look into splitting the inner and outer sensor HV bias - Mike/Gerard
13) Send the problematic prototype cable-T-board assembly to Mike for
investigation - Zhenyu/Mike
14) Develop the QC procedure for Inner cable and T-board assembly - Mike/Maowu
15) Look into the overall large CMN noise, and the abnormal noise of few
channels first appear in the readout - Gerard/Xu
16) Check the FST noise performance at high readout rate - Xu/Zhenyu
17) Sett up the laser test stand to characterize prototype module performance
- Andres/Zhenyu
18) FST slow simulator with efficiency/resolution measured with prototypes
and study tracking performance - Gavin/Shenghui
On Aug 8, 2020, at 10:48 AM, Ye, Zhenyu <yezhenyu AT uic.edu> wrote:
Dear all,
We will have the Weekly FST meeting on Monday starting at 9am EST (BNL local
time).
Bluejeans Meeting URL https://bluejeans.com/101020434
Meeting ID: 101 020 434
https://drupal.star.bnl.gov/STAR/event/2020/08/10/star-forward-silicon-tracker-meeting
0. follow-ups on review and action items
1. Integration
by Rahul Sharma, Felix Archampong
2. Hybrid and T-board by
Maowu Nie, Jianing Dong
3. Simulation Studies by
Gavin Wilks, Shenghui Zhang, Daniel Brandenburg
4. Prototype Module Assembly and Test by Zhenyu Ye
5. Mechanical structure by Yi
Yang
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
_______________________________________________
Star-fst-l mailing list
Star-fst-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/star-fst-l
Attachment:
bias_connections.pdf
Description: Adobe PDF document
-
[Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Ye, Zhenyu, 08/08/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Ye, Zhenyu, 08/10/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Yi Yang, 08/10/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Yi Yang, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/12/2020
- Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time), Yi Yang, 08/12/2020
- Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time), videbaek, 08/12/2020
- Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time), Gerard Visser, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Yi Yang, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Yi Yang, 08/10/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Ye, Zhenyu, 08/10/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
videbaek, 08/11/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Capotosto, Michael, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/12/2020
- Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time), Zhenyu Ye, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Gerard Visser, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
Capotosto, Michael, 08/12/2020
-
Re: [Star-fst-l] Weekly FST meeting, August 10 9am (BNL time),
videbaek, 08/11/2020
Archive powered by MHonArc 2.6.24.