Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets
- From: John Parsons <parsons AT nevis.columbia.edu>
- To: "Ma, Hong" <hma AT bnl.gov>, "Xu, Hao" <haoxu AT bnl.gov>
- Cc: "usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets
- Date: Wed, 8 May 2019 09:43:20 +0200
We are waiting for Andy; will come today.
On 5/8/19 1:58 AM, Ma, Hong wrote:
Has everyone else updated the status?
Penka has been asking for confirmation.
Hong.
*From: *"Xu, Hao" <haoxu AT bnl.gov>
*Date: *Monday, May 6, 2019 at 10:03 PM
*To: *"Ma, Hong" <hma AT bnl.gov>, John Parsons <parsons AT nevis.columbia.edu>
*Cc: *"usatlas-hllhc-lartl2l3-l AT lists.bnl.gov" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
*Subject: *RE: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets
Hi John,
The status has been updated.
Regards,
hao
*From:* Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov> *On Behalf Of *Ma, Hong
*Sent:* Monday, May 06, 2019 5:33 PM
*To:* Parsons, John <parsons AT nevis.columbia.edu>
*Cc:* usatlas-hllhc-lartl2l3-l AT lists.bnl.gov
*Subject:* Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets
I filled the status sheet.
I noticed that most of the columns for Estimated Start and Finish (Column Y and Z) are filled with some dates which are a few months later than column I and J. Do you know who actually filled them?
For tasks that were scheduled to start but haven’t started, I did not do anything.
Hong.
*From: *Usatlas-hllhc-lartl2l3-l <usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov <mailto:usatlas-hllhc-lartl2l3-l-bounces AT lists.bnl.gov>> on behalf of John Parsons <parsons AT nevis.columbia.edu <mailto:parsons AT nevis.columbia.edu>>
*Date: *Monday, May 6, 2019 at 4:06 PM
*To: *"usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <mailto:usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>" <usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <mailto:usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>>
*Subject: *Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets
A reminder to do this asap and let me know when you
are done.
On 5/1/19 5:24 PM, John Parsons wrote:
It is (already) time to fill out the status reports again;
we will from now on do this every month.
Let me know when you are done.
John
-------- Forwarded Message --------
Subject: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets
Date: Wed, 1 May 2019 21:05:00 +0000
From: Novakova, Penka N <penka AT bnl.gov <mailto:penka AT bnl.gov>>
To: usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
<mailto:usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>
<usatlas-hllhc-l2l3ics-l AT lists.bnl.gov
<mailto:usatlas-hllhc-l2l3ics-l AT lists.bnl.gov>>
CC: OConnor, Jennifer <jennifer AT bnl.gov <mailto:jennifer AT bnl.gov>>
Dear All,
The status sheets for the month of April are now available in google
docs
* 6.01 -
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1hwjjZOFyFjMhTOo4-5FGh9r-2Du7JVDsUujLplxGWvaldlk_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=2QEuccTAWFOJNmZGQyce5kWvdCi5kZOGf6DGAVCp3ks&s=mONr8zWvpBZhEUPSdgAuJ5FTd0L8lICF175T55xuP-c&e=
* 6.02 -
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1rRiWNYzxucv0YNwKmd-5FL9yZu-5FXeZMzM-5F8corUDaBnec_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=2QEuccTAWFOJNmZGQyce5kWvdCi5kZOGf6DGAVCp3ks&s=7WdOTK6J3XllDwTK9NXUVInsCf7Tr_0mmenqh6Hph8g&e=
* 6.03 -
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1qgTbEJLy-5FbdWP3OKusH5otphCU8Ix7dOo4PjHOPvp-2D0_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=2QEuccTAWFOJNmZGQyce5kWvdCi5kZOGf6DGAVCp3ks&s=IMmwSVPHWyyoIrC6JpiJiEBLaObAg1p5vJZzP1WGlHs&e=
* 6.04 -
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1E6MuRICREgYKOvOT65QAh9Bnc3PButAxV1q3b-5FcAa78_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=2QEuccTAWFOJNmZGQyce5kWvdCi5kZOGf6DGAVCp3ks&s=f6dBQW3xDdFHoJboOFbDrgV8sfMWsdBTr5lWdJvnhPs&e=
* 6.05 -
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1f0FW-2D0Mn-2DMjFjnOIScb0TnP7pfEYwbBGJj2ubFAA7iY_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=2QEuccTAWFOJNmZGQyce5kWvdCi5kZOGf6DGAVCp3ks&s=qFrjtSxkGfi8mJNo8iSZPql33efL7iPhw2dAEtQaXmU&e=
* 6.06 -
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1yXtpXhSzpGfEoFcWT6eYcTXQqucFcPoFBnlkLpU1mM4_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=2QEuccTAWFOJNmZGQyce5kWvdCi5kZOGf6DGAVCp3ks&s=wUE_ZWrBp0psfCtRXFH4ZzKXa6BDvoTkvsF9t-_lwHc&e=
* 6.07 -
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_1YicazkRHpoZqAwmKV4sRJe8Gpt6a1w9s91wgpZLEwu0_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=2QEuccTAWFOJNmZGQyce5kWvdCi5kZOGf6DGAVCp3ks&s=rald-YdLRrsWp4vk2GRls9hPenv4ARiNbDU9AZo7LvY&e=
* 6.08 -
https://urldefense.proofpoint.com/v2/url?u=https-3A__docs.google.com_spreadsheets_d_17-5FqRjq5vXzPal-2DBgjwo11VNpVgOWTA35beRM95JAM4o_edit-3Fusp-3Dsharing&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=2QEuccTAWFOJNmZGQyce5kWvdCi5kZOGf6DGAVCp3ks&s=L8Uvr74LUC-lak0Shpj8hdEDNdTxHMpQXJI0fTlm4-s&e=
Please remember to update the status online – DO NOT download the files.
The reports are at L2. The CAMs can filter for their name in column D
and the ICs can filter for their institute in column E. The reports
contain activities for April-December 2019 in case some activities have
started earlier.
Please provide status in columns L, M, N, and O. Make sure that you
enter the actual start date for all started activities and finish date
for all activities that are 100% completed, this information is crucial
when we update the schedule in P6. If the activity is completed but you
do not remember the exact start and finish dates you can enter your
best
estimate or copy the dates from the baseline start and finish dates (BL
Project Start/BL Project Finish). In actual start/finish dates do NOT
enter dates after April 30, 2019, this confuses the system.
In addition schedule reports with Gantt charts have been generated and
posted in docdb 734.
Please complete the status reports by Monday, May 6.
We expect that the L2 managers and deputies will notify us (Penka,
Heidi, Carrie) as soon as the status for their system is complete.
Let us know if you have any questions, and also any comments to make
the
process smoother and more user-friendly.
Thank you!
Penka, Heidi, Carrie
Penka Novakova
U.S. ATLAS HL-LHC Project Office
Bldg. 510
Brookhaven National Lab
Upton, NY 11973
Tel. 631-344-2502
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu <mailto:parsons AT nevis.columbia.edu>
Columbia UniversityPhone: (914) 591-2820
P.O. Box 137Fax: (914) 591-8120
Irvington, NY 10533WWW: https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwID-g&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=2QEuccTAWFOJNmZGQyce5kWvdCi5kZOGf6DGAVCp3ks&s=FHQafS0Cd97OngC3gihMT5Lbq4GK0itJomPgd9sc__w&e=
______________________________________________________________________
_______________________________________________
Usatlas-hllhc-lartl2l3-l mailing list
Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov <mailto:Usatlas-hllhc-lartl2l3-l AT lists.bnl.gov>
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-lartl2l3-l
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW:
https://urldefense.proofpoint.com/v2/url?u=http-3A__www.nevis.columbia.edu_-7Eparsons_&d=DwIDaQ&c=aTOVZmpUfPKZuaG9NO7J7Mh6imZbfhL47t9CpZ-pCOw&r=DSVO6Re8kg14S-cQbkBC2zfSx6Yt2GtkcD3fTWOeyfXXTwIA3TKWV-phDKykUKDr&m=xphgEzTkLAaTl2kEsyyadzlJrWBmGoRRzbJec9DG05c&s=YwovNxWUQbXmyDZafUdiMiD57dRs9d_2biXDpfRJk9s&e=
______________________________________________________________________
-
[Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
John Parsons, 05/01/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
John Parsons, 05/06/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Ma, Hong, 05/06/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Xu, Hao, 05/06/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Ma, Hong, 05/07/2019
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets, John Parsons, 05/08/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Ma, Hong, 05/07/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
John Parsons, 05/08/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Ma, Hong, 05/08/2019
- Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets, John Parsons, 05/08/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Ma, Hong, 05/08/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Xu, Hao, 05/06/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
Ma, Hong, 05/06/2019
-
Re: [Usatlas-hllhc-lartl2l3-l] Fwd: [Usatlas-hllhc-l2l3ics-l] Schedule status sheets,
John Parsons, 05/06/2019