Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions
- From: Thomas Schwarz <schwarzt AT umich.edu>
- To: John Parsons <parsons AT nevis.columbia.edu>
- Cc: Michael Tuts <tuts AT pmtuts.net>, "us-atlas-hllhc-pmgmt-l AT lists.bnl.gov" <us-atlas-hllhc-pmgmt-l AT lists.bnl.gov>, "usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov" <usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
- Subject: Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions
- Date: Wed, 1 Mar 2023 16:25:21 -1000
Muons looks good as well.
Tom
On Wed, Mar 1, 2023 at 4:17 PM John Parsons <parsons AT nevis.columbia.edu> wrote:
For LAr looks OK, and the 3 milestones I showed are indeed reproduced in
the xls. You should delete the last 2 rows (XCD4001 and XCD4004), since
these were introduced by the PO to try characterize the "endgame" (and
alignment with DOE CD4, ...) but are messed up.
John
On 3/1/23 9:11 PM, Gustaaf Brooijmans wrote:
>
> Penka extracted Tier 4 and higher milestones to a spreadsheet. I think we can just post this, but take a look nevertheless.
>
>
>
>
>> On Mar 1, 2023, at 9:03 PM, John Parsons <parsons AT nevis.columbia.edu> wrote:
>>
>>
>> BTW, wrt Q1, I had a few LAr examples on slide 19 of my L2 talk:
>>
>> ADC FDR 4/21 -->10/22, FEB2 PDR 10/20 -->12/22, SRTM PDR 10/20 -->01/23
>>
>> On 3/1/23 8:59 PM, John Parsons wrote:
>>> I would still suggest an asterisk that says something like "Very close but not identical to cost at MREFC start on 4/1/2020."
>>> On 3/1/23 8:55 PM, Gustaaf Brooijmans wrote:
>>>>
>>>> It’s in the table!
>>>>
>>>>> On Mar 1, 2023, at 8:52 PM, John Parsons <parsons AT nevis.columbia.edu> wrote:
>>>>>
>>>>>
>>>>> OK, that is fine, but it should be made very clear since otherwise the "answer" will only generate more questions.
>>>>>
>>>>> On 3/1/23 8:49 PM, Gustaaf Brooijmans wrote:
>>>>>> Of course. These are not the baseline numbers. The request is to put “original” base and contingency calculation next to “current”. We have no contingency simulation for the baseline numbers.
>>>>>>> On Mar 1, 2023, at 8:46 PM, John Parsons <parsons AT nevis.columbia.edu> wrote:
>>>>>>>
>>>>>>>
>>>>>>> Same for LAr. I showed in my L2 talk a baseline cost of 19.22M, which includes up to BCP 1027.
>>>>>>>
>>>>>>> John
>>>>>>>
>>>>>>> On 3/1/23 8:00 PM, Thomas Schwarz wrote:
>>>>>>>> For the table in q3, the numbers you have as original are the "FDR" numbers, not the baseline. Is that what you want? There will be some consistency issues - at least for muons. Our baseline starts at BCP 1028.
>>>>>>>> Tom
>>>>>>>> ===================
>>>>>>>> Tom Schwarz
>>>>>>>> Associate Professor
>>>>>>>> Department of Physics
>>>>>>>> University of Michigan
>>>>>>>> Office: 734-764-8941
>>>>>>>> Lab: 734-763-7805
>>>>>>>> schwarzt AT umich.edu <mailto:schwarzt AT umich.edu>
>>>>>>>> ===================
>>>>>>>> On Wed, Mar 1, 2023 at 1:57 PM Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu <mailto:gusbroo AT nevis.columbia.edu>> wrote:
>>>>>>>> Hi,
>>>>>>>> I set up a google sheets doc so everybody can edit:
>>>>>>>> https://urldefense.com/v3/__https://docs.google.com/presentation/d/1pc9McRumCppvOabd6qAar9a6aF741cOPTeVNOuYmd6M/edit?usp=sharing__;!!P4SdNyxKAPE!HcxWtBiLR_F2zarA9vkhI4kh3I8cvAubC0ljF9elb5ScOQ6_53IcGjFtRpPW4xP29blI9OditTw8rBd3kyWDcTLOxCr7IwW-ulDsAS3Uqcs62gvXPIfkyg$ <https://urldefense.com/v3/__https://docs.google.com/presentation/d/1pc9McRumCppvOabd6qAar9a6aF741cOPTeVNOuYmd6M/edit?usp=sharing__;!!P4SdNyxKAPE!BC6GdmUO_ZA84FfAZ2T2DDE33hHpPT5YDqKUjWMGEgUDEVsFkqVS-xTHgGnKeBk5Obxe0Plc9kAB5Cad9xgmdhTZM4UCLP-YzcTKhQJrpijN-YM5RDy5_g$>
>>>>>>>> I have answered question 3. I think Penka was going to work on #1
>>>>>>>> after Alexei asked his question. #2 is for Chris and I think
>>>>>>>> between you and Hal you should be able to answer #4. Hal has slides
>>>>>>>> on this from the FDR.
>>>>>>>> Best,
>>>>>>>> Gustaaf
>>>>>>>>> On Mar 1, 2023, at 6:40 PM, Michael Tuts <tuts AT pmtuts.net
>>>>>>>>> <mailto:tuts AT pmtuts.net>> wrote:
>>>>>>>>>
>>>>>>>>> Hi Gustaaf,____
>>>>>>>>>
>>>>>>>>> I can put together something on subaward management.____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> Do you have the original breakdown for 3? I have that based on the
>>>>>>>>> official breakdown as in our original award (I also put the
>>>>>>>>> breakdown for 1057 that I used in one of my slides), so could also
>>>>>>>>> do that if it helps.____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> Maybe Hal could take what we get from the L2s and flesh out the
>>>>>>>>> last point on system engineering and interface management? I will
>>>>>>>>> make the subaward management slide.____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> Can ask about the schedule distributions – one thought is that we
>>>>>>>>> posted Chris’ talk in the management breakout section … maybe they
>>>>>>>>> looked there and found something?____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> Cheers, Mike____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> *From:* Gustaaf Brooijmans <gusbroo AT nevis.columbia.edu
>>>>>>>>> <mailto:gusbroo AT nevis.columbia.edu>>
>>>>>>>>> *Sent:* Wednesday, March 1, 2023 6:33 PM
>>>>>>>>> *To:* Michael Tuts <tuts AT pmtuts.net <mailto:tuts AT pmtuts.net>>;
>>>>>>>>> Meyer, Chris <cjmey AT iu.edu <mailto:cjmey AT iu.edu>>
>>>>>>>>> *Cc:* us-atlas-hllhc-pmgmt-l AT lists.bnl.gov
>>>>>>>>> <mailto:us-atlas-hllhc-pmgmt-l AT lists.bnl.gov>;
>>>>>>>>> usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>>>>>>>>> <mailto:usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
>>>>>>>>> *Subject:* Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2
>>>>>>>>> Director’s Review Homework Questions____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> Hi Mike,____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> I can produce the table for item #3 easily. I’m not sure what #2
>>>>>>>>> means - I don’t think we showed them graphs for MC schedule
>>>>>>>>> distributions, so maybe you can ask them what they mean by that? But I guess Chris can put a few of the PRA output graphs on a few
>>>>>>>>> slides?____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> Best,____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> Gustaaf____
>>>>>>>>>
>>>>>>>>>
>>>>>>>>>
>>>>>>>>> ____
>>>>>>>>>
>>>>>>>>> On Mar 1, 2023, at 6:28 PM, Michael Tuts <tuts AT pmtuts.net
>>>>>>>>> <mailto:tuts AT pmtuts.net>> wrote:____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>>> Hi All,____
>>>>>>>>>
>>>>>>>>> Attached are the homework questions. Most are addressed to the
>>>>>>>>> PO it looks like. The one area where L2s can contribute is
>>>>>>>>> part of the last one on system engineering practices and
>>>>>>>>> interface management – please put together some response for
>>>>>>>>> that.____
>>>>>>>>>
>>>>>>>>> ____
>>>>>>>>>
>>>>>>>>> Thanks, PO____
>>>>>>>>>
>>>>>>>>> ____
>>>>>>>>>
>>>>>>>>> *From:*LeCompte, Tom <lecompte AT slac.stanford.edu
>>>>>>>>> <mailto:lecompte AT slac.stanford.edu>>
>>>>>>>>> *Sent:*Wednesday, March 1, 2023 6:19 PM
>>>>>>>>> *To:*Michael Tuts <tuts AT nevis.columbia.edu
>>>>>>>>> <mailto:tuts AT nevis.columbia.edu>>
>>>>>>>>> *Cc:*Victor Krabbendam <VKrabbendam AT lsst.org
>>>>>>>>> <mailto:VKrabbendam AT lsst.org>>; Gutta, Rajendra Rao
>>>>>>>>> <rgutta AT bnl.gov <mailto:rgutta AT bnl.gov>>; Marco Verzocchi
>>>>>>>>> (marco.verzocchi AT gmail.com <mailto:marco.verzocchi AT gmail.com>)
>>>>>>>>> <marco.verzocchi AT gmail.com
>>>>>>>>> <mailto:marco.verzocchi AT gmail.com>>; Sarah Eno <eno AT umd.edu
>>>>>>>>> <mailto:eno AT umd.edu>>; Ted Liu (thliu AT fnal.gov
>>>>>>>>> <mailto:thliu AT fnal.gov>) <thliu AT fnal.gov
>>>>>>>>> <mailto:thliu AT fnal.gov>>; Darin Acosta <dea6 AT rice.edu
>>>>>>>>> <mailto:dea6 AT rice.edu>>; Alexei N. Safonov <safonov AT tamu.edu
>>>>>>>>> <mailto:safonov AT tamu.edu>>; Denisov, Dmitri <denisovd AT bnl.gov
>>>>>>>>> <mailto:denisovd AT bnl.gov>>
>>>>>>>>> *Subject:*March 1-2 Director’s Review Homework Questions____
>>>>>>>>>
>>>>>>>>> ____
>>>>>>>>>
>>>>>>>>> Hi Mike-____
>>>>>>>>>
>>>>>>>>> We have just a handful of questions:____
>>>>>>>>>
>>>>>>>>> * We would like to see a high-level (say Levels 1 and 2)
>>>>>>>>> milestone-based comparison ofthe original and revised
>>>>>>>>> schedules.____
>>>>>>>>> * We saw graphs of the schedule distributions from Monte
>>>>>>>>> Carlo runs; we would like to see similar graphs for cost____
>>>>>>>>> * We would like to see a table with four columns - original
>>>>>>>>> base and contingency and revised base and contingency.
>>>>>>>>> Rows should be at the the L2 level of detail.____
>>>>>>>>> * Please prepare a few slides to address Question K, "Is____
>>>>>>>>> * the project adhering to best practices in systems
>>>>>>>>> engineering, interface management, and subaward
>>>>>>>>> management?:____
>>>>>>>>>
>>>>>>>>> This should not sum up to more than a few slides.____
>>>>>>>>>
>>>>>>>>> The expectation is that Management, Cost & Schedule will not
>>>>>>>>> meet tomorrow, and instead people will join the various
>>>>>>>>> technical subcommittees. If this is a problem, let me know and
>>>>>>>>> we can adjust.____
>>>>>>>>>
>>>>>>>>> If you have questions, please email me or call at
>>>>>>>>> 331-803-0446.____
>>>>>>>>>
>>>>>>>>> Cheers,____
>>>>>>>>>
>>>>>>>>> Tom____
>>>>>>>>>
>>>>>>>>> _______________________________________________
>>>>>>>>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>>>>>>>>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>>>>>>>>> <mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
>>>>>>>>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l <https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l>____
>>>>>>>>>
>>>>>>>>> __ __
>>>>>>>>>
>>>>>>>> _______________________________________________
>>>>>>>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>>>>>>>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>>>>>>>> <mailto:Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov>
>>>>>>>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l <https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l>
>>>>>>>> _______________________________________________
>>>>>>>> Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
>>>>>>>> Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
>>>>>>>> https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
>>>>>>>
>>>>>>> --
>>>>>>> ______________________________________________________________________
>>>>>>>
>>>>>>> John Parsons
>>>>>>> Nevis Labs, Email: parsons AT nevis.columbia.edu
>>>>>>> Columbia University Phone: (914) 591-2820
>>>>>>> P.O. Box 137 Fax: (914) 591-8120
>>>>>>> Irvington, NY 10533 WWW: https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!HcxWtBiLR_F2zarA9vkhI4kh3I8cvAubC0ljF9elb5ScOQ6_53IcGjFtRpPW4xP29blI9OditTw8rBd3kyWDcTLOxCr7IwW-ulDsAS3Uqcs62gsLQE7AjQ$
>>>>>>>
>>>>>>> ______________________________________________________________________
>>>>>>>
>>>>>
>>>>> --
>>>>> ______________________________________________________________________
>>>>>
>>>>> John Parsons
>>>>> Nevis Labs, Email: parsons AT nevis.columbia.edu
>>>>> Columbia University Phone: (914) 591-2820
>>>>> P.O. Box 137 Fax: (914) 591-8120
>>>>> Irvington, NY 10533 WWW: https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!HcxWtBiLR_F2zarA9vkhI4kh3I8cvAubC0ljF9elb5ScOQ6_53IcGjFtRpPW4xP29blI9OditTw8rBd3kyWDcTLOxCr7IwW-ulDsAS3Uqcs62gsLQE7AjQ$
>>>>>
>>>>> ______________________________________________________________________
>>>>>
>>>>
>>>>
>>
>> --
>> ______________________________________________________________________
>>
>> John Parsons
>> Nevis Labs, Email: parsons AT nevis.columbia.edu
>> Columbia University Phone: (914) 591-2820
>> P.O. Box 137 Fax: (914) 591-8120
>> Irvington, NY 10533 WWW: https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!CAEHZciw-2yIZxUqE2s9nbNtc8FExnN0PZvI3LjGLAqDLTubEW3Uq_jk_A1xVqr2QEBJ36-LEUXg2e1bf4ycUGlElpYaR7t5ifDH3aM9CLHpphPl6e8dsQ$
>>
>> ______________________________________________________________________
>>
>
--
______________________________________________________________________
John Parsons
Nevis Labs, Email: parsons AT nevis.columbia.edu
Columbia University Phone: (914) 591-2820
P.O. Box 137 Fax: (914) 591-8120
Irvington, NY 10533 WWW: https://urldefense.com/v3/__http://www.nevis.columbia.edu/*parsons/__;fg!!P4SdNyxKAPE!CAEHZciw-2yIZxUqE2s9nbNtc8FExnN0PZvI3LjGLAqDLTubEW3Uq_jk_A1xVqr2QEBJ36-LEUXg2e1bf4ycUGlElpYaR7t5ifDH3aM9CLHpphPl6e8dsQ$
______________________________________________________________________
_______________________________________________
Usatlas-hllhc-l2deputymgmt-nsf-l mailing list
Usatlas-hllhc-l2deputymgmt-nsf-l AT lists.bnl.gov
https://lists.bnl.gov/mailman/listinfo/usatlas-hllhc-l2deputymgmt-nsf-l
-------------------------------------
Tom Schwarz
Associate Professor
Department of Physics
University of Michigan
Office: 734-764-8941
Lab: 734-763-7805
schwarzt AT umich.edu
-------------------------------------
Tom Schwarz
Associate Professor
Department of Physics
University of Michigan
Office: 734-764-8941
Lab: 734-763-7805
schwarzt AT umich.edu
-------------------------------------
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions
, (continued)
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Gustaaf Brooijmans, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Gustaaf Brooijmans, 03/01/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
John Parsons, 03/01/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Gustaaf Brooijmans, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, John Parsons, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Gustaaf Brooijmans, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, John Parsons, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, John Parsons, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Gustaaf Brooijmans, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, John Parsons, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Thomas Schwarz, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Stephanie Majewski, 03/01/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions,
Gustaaf Brooijmans, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Gustaaf Brooijmans, 03/01/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [External] March 1-2 Director’s Review Homework Questions, Gustaaf Brooijmans, 03/02/2023
-
Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [External] Re: March 1-2 Director’s Review Homework Questions,
Michael Tuts, 03/02/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] [External] Re: March 1-2 Director’s Review Homework Questions, Evans, Harold G., 03/02/2023
- Re: [Usatlas-hllhc-l2deputymgmt-nsf-l] March 1-2 Director’s Review Homework Questions, Michael Tuts, 03/02/2023
Archive powered by MHonArc 2.6.24.